HomeMy WebLinkAbout2017.04.032017 Bid Opening Results
March 22, 2017 Bid Opening
Dust Control
Seal Coat
1
Dust Control Project
Approximately 25 miles of gravel roads
2008 to Present – Dust control applied to all Gravel roads twice per year
Provides dust control for up to 2 months with each application
Mostly
positive feedback from residents
2
Dust Control Project
Cooperation with other cities:
May Township: Keystone Ave. N. cost share
City of Grant: Hugo/Grant bid together
120th St. N. cost share
3
Dust Control Project
LOW BID (Envirotech) = $0.837/gal
2nd Bid received by Northern Salt- $0.871/gal
2017 price is $0.05/gallon less than 2016
2017 price is $0.12/gallon less than 2015
4
Dust Control Project
Desired Action
Public Works Staff recommends Council approve a 2017 Dust Control contract with Envirotech Services to apply Calcium chloride at $0.837/gal.
5
Seal Coat Project
6
Project Location
7
Seal Coat Project
Mn/DOT seal coat specifications
Extensive bituminous patching in project area prior to seal coat application
Increased sweeping frequency after seal coat application
8
Seal Coat Project
3 Bids Received
Allied Blacktop Co. - $209,781.94
Pearson Brothers Inc. - $221,900.46
Astech Corp. – $237,969.78
9
Seal Coat Project
Funding:
“State Aid Maintenance” dollars
General tax levy dollars
10
Seal Coat Project
Desired Action
Public Works Staff recommends Council approve a 2017 Seal Coat contract with Allied Blacktoping Inc. for $209,781.94