Tonight we are holding a public hearing on a request for a minor subdivision and CUP
1
Highway 61
170th Street
CSAH 8
Henna Ave
Site
130th Street
Goodview Ave
Keystone Ave
Homestead Ave
137th Street
The property is located north of Frenchman RD (County Road 8) and west of Everton Ave. N.
2
City Owned Outlot
The property to the north is zoned Low Density Multiple Family Residential (R-4) and occupied by the Pineview Meadows townhome development. The properties to the east, south, and west
are zoned Single Family Detached Residential (R-3) and occupied by the Country Ponds, Beaver Ponds, and Birch Tree Ponds residential developments. The properties to the west, across
Highway 61, are zoning General Industrial (I-3) and are occupied by industrial uses. There are also a few vacant parcels to the east that are also zoned Single Family Detached Residential
(R-3).
3
Description of Request
Approval of a preliminary plat and planned unit development (PUD)
The property totals 216 acres, 146 buildable acres, comprising of 6 parcels.
Use of the City owned outlot is proposed,
but not include in acreage or density calculations
The preliminary plat includes 319 single family units and 10 outlots.
Tonight the City Council will also take action on the EAW and
wetland replacement plan.
4
Show locations of streets.
Blue is ponds.
The light green is wetlands
The darker green is upland, as shown in the park areas and trial locations.
Most of the outlots will be
owned by the City, except the homes in the street loops.
I will go over more specifics of the development through my presentation.
5
Background
A sketch plan was presented to the Commission and City Council.
They commented on the following:
Comfortable with the use of the City-owned outlot
Reconstruction of 130th Street
Provide
landscape buffers
Desire to preserve trees
Appreciated the proposal for water reuse
Concerns over the long road connecting the north and south ends of the development
Concerns over
the 45 ft. wide lots
Liked the trail system and park location
Questions about park improvement phasing
6
Background, Cont.
Resident Comments and Concerns:
Proposed density of the project
Proposed lot sizes
Traffic
Location of proposed stormwater ponds
They wanted to ensure that the Commissions and City
Council kept the neighboring properties in mind during the approval process.
7
Environmental Review
An EAW is required for any residential project over 250 units.
The developer has prepared an EAW for the development.
An EAW analyzes the effect the development has on the environment
in regards to land use, geology, water resources, wildlife, air, noise, and transportation.
30-day comment period ended March 29th
The applicant is proposing 319 new homes on this property. The minimum threshold for a mandatory Environmental Assessment Worksheet (EAW) per MN State Statute is 250 units, therefore,
an EAW is required.
The developer has been working with City staff to prepare an EAW for the development. An EAW is a document that analyzes, at a preliminary level, the effects a
development has on the environment in regards to land use, geology, water resources, wildlife, air, noise, and transportation. If there are significant impacts, mitigation measures should
be made.
The EAW is regulated by the Environmental Quality Board (EQB) with the City acting as the Responsible Governing Unit (RGU) responsible for the preparation of the EAW and determining
if an EIS is necessary.
There is a 30-day comment period where the EAW is sent to several local, state and federal agencies and notice is sent to the surrounding properties.
The
comment period ended March 29th and tonight the Council would consider the comments from the agencies, as will as comments from the public, and determine if an EIS is necessary.
No
formal approval of the plan can occur until the EAW process is complete. And staff would anticipate the developer to make changes to the plan to address the comments generated from the
EAW process.
8
Environmental Review, Cont.
There were specific items identified in the EAW:
Floodplain and wetland impacts were anticipated
Mitigation measures are in place and are required to meet RCWD rules
Stormwater management
on-site will handled through drainage ponds and stormwater treatment.
Water re-use
Adequate sewer and water is available to the site.
Traffic mitigation
Short term – signal timing
and geometric improvements
Long term – Highway 61 improvements and
turn lanes
Floodplain boundaries can be revised
1.3 acres, out of the 57 acres total of wetlands are proposed to be impacts
The stormwater management plan is also required to meet the RCWD Rules.
Traffic – as approved by MnDOT
There were other items were addressed
Wildlife, connected wetlands and openspace for habitat
Archeological resourced, which there were none
The development
would not generate noise exceededing the state noise standard
If it was determined if that an EIS was not necessary the applicant can more forward with permitting and platting the land.
9
Environmental Review, Cont.
Some agencies have commented on specific items that should be considered when the property develops.
The Planning Commission held a public hearing on the EAW at its March 23, 2017, meeting.
Staff has prepared formal responses to all of the comments received throughout the process.
The EAW has identified areas where potential environmental effect exists and has incorporated
the appropriate mitigation measures into the project plan.
Staff analyzed the EAW and project plan as it relates to State Rules and finds the project does not have the potential for
significant environmental impacts, and therefore staff does not recommend an environmental impact statement (EIS).
10
Wetland Replacement Plan
Approximate 57 acres of wetland
1.32 acres of wetland proposed to be impacted for road construction
Purchasing wetland bank credits
The Technical Evaluation Panel (TEP) reviewed the
application and found that it meets all requirements for avoiding, minimizing, and replacing wetland impacts
11
Planned Unit Development (PUD)
The use of the PUD zoning allows:
Zoning ordinance flexibility to create a master planned development.
Enhanced flexibility to develop a site through the relaxation of zoning district
standards.
Greater variety of land uses, internal transfers of density, construction phasing, and a potential for lower development costs.
In exchange for this enhanced flexibility,
the City has the expectation that the development plan will result in a significantly higher quality and more sensitive proposal than would have been the case with the use of other,
more standard zoning districts.
The PUD is tied to a specific general plan
12
PUD, Cont.
The applicant is asking for various of lot sizes to allow for a variety of housing products.
Flexibility for reduced lot width and setbacks.
The Council has seen these lot sizes in developments
such as, Victor gardens, Fable Hill, and Clearwater Cove.
The maximum development density for a PUD in the R-3 zoning district is 4 units per 1 acre.
The applicant is proposing a
residential net density of 2.2 units per 1 acre, which fits the requirements of a PUD.
Although the applicant is requesting flexibility on lot sizes and setbacks, the density meets
the ordinance standards.
13
In exchange for this flexibility, the developer is:
Designing a more sensitive proposal, with less density, than would have been the case with the use of the standard R-3 zoning district.
Providing a public park within the development, with improvements that exceed City standards.
Providing a public trail to connect to existing trails in the adjacent developments. Preserving
and enhancing natural features with the trail system that meanders through the development.
Providing a landscaping plan that exceeds City standards.
Preserving existing significant
trees on the property.
Creating a stormwater reuse irrigation project within the development.
Incorporating architectural design guidelines for the homes in the development
14
A homeowners association (HOA) is proposed for the development. There are three housing styles (single family detached homes, smaller single family detached homes, Villa homes) that
are proposed within the development that would have their own homeowners association. All of the homes would be part of a Master HOA which will be established for the development to
own/operate/maintain community areas, landscaping, and the water re-use system. The HOA would also establish an Architectural Review Committee (ARC) to review and approve the home designs
per architectural design guidelines.
This entire area will be owned by the City and used as a public park, with improvements and trails.
The applicant is showing sidewalks along
one side of each street within the development. The plan shows a trail systems that will connect to the existing trail in Beaver Ponds, extends through the development bordering the
proposed park, and will provide pedestrian access to 140th Street (CSAH 8). The applicant is showing a trail system that connects the residential areas to the park, as well as, to the
adjacent neighborhoods and other nearby parks. The trail system will provide a recreational experience that takes advantage of the view sheds of the natural areas.
Stormwater will be
managed through ponds and Stormwater Reuse
The development is proposed to be completed in 5 phases. Generally from the south to the north.
The grading will happen in two phases. Generally
all of the property to south will be graded with the first phase and the remaining property to the north will be graded with the second phase.
15
Streets and
Access
The applicant is proposing 3 access locations along 130th Street.
And connections to 137th Street to the west, Flay Avenue to the north, and 135th Street to the east.
Highway 61 and
130th Street is a signalized intersection and was designed assuming the development of the property.
Long range plans for Highway 61 are to expand it to a 4 lane highway with a median.
The applicant is showing a road connecting the north and south areas of the development. The applicant has done a good job addressing the concerns that the Council and Commission had
regarding the previous plan showing a long road connecting the north and south portions of the development.
16
130th Street Improvements
Currently a two-lane, rural section roadway
Upgrade to a two-lane, urban section roadway
Design
Roundabout considered at Flay Avenue
8 foot wide bituminous trail on the north side
Cost
Share/Timing
130th is shown as a future improvement in the CIP
Staff is discussing with the applicant the appropriate cost share and timing of the improvements.
The developer cost
responsibilities will be identified and included in the development agreement for the first phase of the project.
As the proposed development moves forward, nearly all of the roadway segment between Highway 61 and Goodview Avenue will be developed on the north and south sides. 130th Street is currently
a two-lane, rural section roadway. Staff recommended, and the City Council and Commissions agreed, during the sketch plan that the upgrade of 130th Street to an urban-section road between
Highway 61 and Goodview Avenue should be completed with the development as outlined in the City’s long-range plans.
Staff has been working with the applicant on a number of items
regarding the improvement/reconstruction of 130th Street. The design of the road is being discussed and the addition of a roundabout at Flay Avenue and 130th Street is being considered.
The design will include an 8 foot bituminous trial on the north side.
Staff is discussing with the applicant the appropriate cost share and timing of the improvements. Staff is anticipating
a there be a City cost share in the project. 130th Street is shown on the road CIP as a future improvement. The developer cost responsibilities will be identified and included in the
development agreement for the first phase of the project.
The results of the EAW indicate the development can be accommodated, provided a number of improvements to 130th Street are
completed. The existing signal timing at TH 61 and 130th Street will also require monitoring, with potential changes made by MnDOT.
We have not come up with a cost share formula to
recommend to the City Council, but the developers frontage along 130th Street is roughly ½.
** the developer of Beaver Pond contributed to 130th when they developed.
17
Park Dedication
7.8 acres of park land
sports field area
active park area with playground, multi-sport court, and park shelter
1.5 miles of trails and boardwalks in a passive park area
18
Park Dedication
Above and beyond their required park dedication, the developer is:
Grading and landscaping a public park within the neighborhood.
Providing a public trail to connect to existing trails
in the adjacent developments.
Preserving and enhancing natural features with an off-road trail system that meanders through the development.
Preserving existing significant trees on
the property.
There are park improvements identified that they City is would have the option to install at some time.
Irrigation
Parking lots
Shelter
Sports Court
Play Equipment
Etc.
For the overall development, they are planning 5 phases.
Phasing Plan
Phase 1: city city-owned outlot and areas south of power lines (soccer field)
Phase 2: areas north of power
lines (north park, trails, etc)
19
3-22-17 Parks Commission Meeting
Favorable of the park plan, off road trail system, and phasing plan.
Comfortable with the use of the City owned outlot.
Questioned if the amount of park dedication, paid by fee, would
cover the cost of the improvements.
Wanted to continue to work with the applicant on the timing of the park improvements that the City would be responsible for.
Additional meetings
will likely be held.
Recommended approval of the park dedication proposal.
20
3-23-17 Planning Commission Meeting
8 residents spoke during the public hearing
Questions/Concerns
Number of lots created
Connections to the park
Traffic
Buffers/preservation of trees
Wildlife
Drainage/flooding
-Staff stated that the density of the development is less that was is allowed in the R-3 Zoning District.
-The developer stated that they would add a sidewalk along 137th Street to
connect to the neighborhood to the west and will work with staff on additional connections to the park from the adjacent neighborhood.
-One resident asked for a tree line between her
house, in the County Ponds neighborhood to the west, be preserved to create a buffer from the proposed pond and homes.
-There were a few residents concerned about the wildlife being
lost when the development is constructed. The EAW prepared for the development proposes mitigation measures for the wildlife during construction and did not anticipate significant loss
in wildlife.
-There were also a few residents concern about the drainage and flooding of their property because of the development. City Engineer, Mark Erichson, stated that the drainage
will remain on the development property and is required to meet all stormwater management regulations determined by the Rice Creek Watershed District (RCWD).
21
3-23-17 Planning Commission Meeting
Generally liked the plan and was pleased with the development layout, mix of housing products, park features, and the use of stormwater reuse for irrigation.
The Planning Commission
recommended approval of the requests, subject to the conditions on the resolutions, and the addition of two conditions:
The developer shall work with staff on trail a connection to the
County Ponds neighborhood to the west.
The developer shall work with staff regarding moving the pond back from the rear lot lines of the County Ponds neighborhood to the west and review
the trees in the area.
The vote was 5 approvals and 1 abstention. The abstention resulted from a concern on the traffic along Highway 61.
The Planning Commission requested to have a discussion with staff regarding the future of Highway 61.
Staff has been working with the developer on the buffer and the trail connection.
22
The developer agreed to add a sidewalk along 137th Street.
The developer agreed to work with staff on additional connections to the park.
Existing area shown on the plans between
the ponds on the rear lot lines is 15 feet.
The developer is proposing to slightly increase the area from 15 feet to 20 feet from the rear lot lines of Country Ponds.
Staff visited
the property and most of the area is covered in brush and did not find significant trees. The EAW did not note any protected areas.
23
Conclusion
Staff analyzed the EAW and project plan as it relates to State Rules and finds the project does not have the potential for significant environmental impacts.
The TEP reviewed the wetland
replacement plan at it meets all WCA requirements.
Staff believes that the layout of the proposed Adelaide Landing PUD general plan exceeds the City’s standards for residential developments.
The rezoning/PUD is consistent with the Comprehensive Plan in terms of land use and density.
It is in staff’s opinion that the Adelaide Landing PUD general plan has offered a creative
and efficient method to planning the site, all which meets the intent of the PUD ordinance.
24
Recommendation
Proposed Motions:
Staff recommends the City Council move to approve the findings of fact and conclusions for the EAW and adopt the resolution approving the issuance of a negative declaration
for the need of an environmental impact statement (EIS).
Staff recommends the City Council move to approve the wetland replacement plan.
Staff recommends the City Council move to table
the preliminary plat and PUD application until May 1, 2017, as requested by the applicant.
Staff welcomes any Council discussion and feedback to the applicant and staff on the preliminary
plat and
PUD applications
25
26
PUD, Cont.
Lot Size
*Requested PUD flexibility highlighted in grey
The applicant is asking for a variety of lot sizes for various housing products.
Min lot size of 5,850 sqf, where 10,400 is allowed by ordinance.
Min lot width of 45 ft, where 80
feet is allowed by ordinance.
The Planning Commission has seen these lot sizes in developments such as, Victor gardens, Fable Hill and Clearwater Cove.
27
PUD, Cont.
Setbacks
*Requested PUD flexibility highlighted in grey
28
29
Existing area shown on the plans between the ponds on the rear lot lines is 15 feet.
The developer is proposing to slightly increase the area from 15 feet to 20 feet from the rear lot
lines of Country Ponds.
Staff visited the property and most of the area is covered in brush and did not find significant trees. The EAW did not note any protected areas.
The developer
agreed to add a sidewalk along 137th Street.
The developer agreed to work with staff on additional connections to the park.
30