130th Street has been identified as a roadway for improvement, however not on CIP
Adelaide Landing has started construction on their initial phase
Development Agreement Requires 44%
of projects costs to be paid to the City ($1,566,520)
1/3 due at each of the first three phases ($521,840)
Beaver Ponds previously contributed funds used for 130th Street and TH 61 Improvements
Background
3
Urban Section with Roundabout at Flay Avenue and 130th Street
2019 Construction
Pedestrian Trail
Affect on CIP
Wetland Delineation
Soil Borings
130th Street Considerations
4
Recommendation/Next Steps
Further Evaluate Design Alternatives and coordinate with development team
Complete wetland delineation
Complete soil borings
Meet with adjacent land owners
5