HomeMy WebLinkAbout2017.09.18 130th Street Improvement Project September 18, 2017 1 Sunset Lake 130th Street Project Location 2 130th Street has been identified as a roadway for improvement, however not on CIP Adelaide Landing has started construction on their initial phase Development Agreement Requires 44% of projects costs to be paid to the City ($1,566,520) 1/3 due at each of the first three phases ($521,840) Beaver Ponds previously contributed funds used for 130th Street and TH 61 Improvements Background 3 Urban Section with Roundabout at Flay Avenue and 130th Street 2019 Construction Pedestrian Trail Affect on CIP Wetland Delineation Soil Borings 130th Street Considerations 4 Recommendation/Next Steps Further Evaluate Design Alternatives and coordinate with development team Complete wetland delineation Complete soil borings Meet with adjacent land owners 5