MINUTES OF PROCEEDINGS OF THE HUGO PLANNING COMMISSION
JULY 9, 1974
The meeting was called to order at 8:08 P.M. by Chairman Larry Ehret.
Members present were Spitzer, Ehret, Peloquix, Leroux (9:12) , Schletty,
Rosenquist and Johnson (9:00) . Also present was Dennis Welch from the
Washington County Planning Department.
Motion made by Spitzer, and seconded to dispense with the reading
of the minutes of the June 26, 1974 meaning. Motion carried.
Motion made by Spitzer, seconded by Peloquix, to approve the minutes
of the June 26, 1974 meeting. Motion carried.
TAUER SPECIAL USE PERMIT
Mr. Ehret read letter subj*itted from the Sanitary Engineering
Laboratories, Inc. who conducted anCanalysis of the existing Tauer
sewer disposal system. Mir. Ehret also read report submitted from
the Planning Department.
An attorney representing Mr. Tauer said he takes acception to many
of the things ix Schwab' s report: Mr. Tauer was not asked to furnish
any specific plans and he did furnish everything he was asked.
Original plans included the apartment. The comprehensive land use
Plan is not in effect yet. He felt Schwab' s report was totally
inadequate and unfair and it should be disregarded.
Mr. Welch discussed the reasonings of Mr. Schwab' s report.
Spitzer explained the Comprehensive Plan and the background of the
Tauer's request for a Special Use Permit.
The real problem is do they want a multiple family dwelling ix a
rural area.
Tauer's Attorney - The basic purpose of the Comprehensive Plan is
for future uses, and this is something that is in existanee. He
feels they haven't destroyed anything in this area and doesn' t think
its going to destroy the Comprehensive Land Use Plan.
Motion made by Spitzer, seconded by Rosenquist, that the Tauer
Special Use Permit be recommended for denial as it does not conform
to the Comprehensive Plan and none of the purposes contemplated by
the Comprehensive Plan would be served by this request.
Members for: Peloquix, Ehret, Schletty, Rosexquist and Spitzer.
Motion carried.
MINIATURE GOLF COURSE SPECIAL USE PERMIT
Ehret read letter from the Rice Creek Watershed approving their
permit to pond the water in the picnic area. He also read letter
from the Planning Department.
David Kirscht from the David A. Kirscht Assoc. , Inc. Landscape
Architects represented the owners of the A&W.
-2_
Mr. Kirscht stated that they had done a field survey of the property
and they had contacted Mr. Kuusisto's office and they furnished the
information requested. He worked with the Rice Creek Watershed and
they came up with a plan to drain the water into a low area and then
depend of percolation. The plan has not been submitted to the City
Engineer. Twenty percent at the :;most would be paved in the golf
course area. Shallow ditches could be used for drainage and catch
basins could be put in xt1 a .lateT;Alate.
Schletty didn't go along with their drainage plan.
Kirscht said they could keep the water on their property by grading.
.
A new lighting proposal was submitted which would be double the cost
bt 1/3 the operating cost. The light bulb is in the housing,
g' no
refractors,
with adjustable reflectors. They will guarantee that
the neighbors will not see the light source. There will be 25'
poles on the sides with a 40' pole ix the center.
A question was asked whether they were going to have security
lighting. They haven't considered this aspect but they would
do what the City required.
They would like to stage this development.
A discussion was held on delineated turf or crushed rock versus
asphalt walk.
No fill will be used, just grading.
Welch said they needed a detailed plant list because landscaping
was recommended to be within one year and there would not be any
way to check to see that it was completed. Kirscht said they
didn't have a list because with the new lighting the shrubbery
plan is changed.
g S
Motion made by Spitzer, seconded by Rosexquist, recommending issuanc&
of a Special Use Permit to the A&W subject to the following conditions:
1. Hours of operation shall be confined to the hours of 9:00 a.m.
to 10:00 p.m. weekdays and 9:00 a.m. to 11:00 p.m. Friday and
Saturday June through August and to the hours of 9:00 a.m. and
9:00 p.m. weekxigbts and 9:00 a.m. and 11:00 P.m. Priday and
Saturday for the balance of the year.
2. Lighting shall be installed in accordance with the planp resented
to the Planning Commission and ix no instance shall cause an
illumination shall not exceed 5 foot candles at the exterior of
the golf course.
3. The complete grading and drainage plan be submitted and approved
by the City Engineer.
-3_
4. Adequate sanitary facilities providing for two separate
toilet facilities shall be installed.
5. The six foot high redwood fence proposed on the east end of
the property shall be set back from the property line not less
than three feet.
6. All tke exterior screening ands , site preparations required
for surface drainage shall be completed within one year
following issuance of the Special Use Permit.
7. In addition to the screenking shown on the plan, additional
screening shall be provided on the north property lime east
of the existing garage on the adjacent property.
8. All driveway aid parking surface areas shall be blacktopped.
All walkways within the miniature golf course shall be delineated
turf or gravel and shall not be blacktopped or concrete.
9. The applicant shall be required to post a bond in the amount
of $5,000 to insure compliance with the exterior screening,
surface water drainage site preparation, and parking area
surface requirements.
10. This permit shall be reviewed,in a period not more than 18
months after its issuance,by the Planning Commission to assess
the degree of compliance with the plan as submitted. Permission
for all improvement not installed as of that date shall be revoked.
Members for: Peloquim, Johnson, Ehret, Rosenquist, Spitzer and
Leroux. Schletty voted no. Motion carried.
EDWARD WAUGH - TRAEGER'S SUBDIVISION
Mr. Ehret read letter from Kuusisto and Schwab. Mr. Waugh submitted
a new proposed plat and a letter from the Rice Creek Watershed.
A representative for Mr. Waugh made the following statements:
- Lot one is an out lot.
- Lot 8 (7 on the new plat) increased in size.
- Grading plan on their plat.
- Discussed 17' easement along the south for a roadway.
y
A discussion was held on the term flood proofing mentioned in the
letter from the Rice Creek Watershed. Ehret felt they meant the
main floor of the building would have to be above 930.
Mr. Welch was directed to contact the Washington County Engineer
to get a written report on right,-of-way for County Road 8A and
submit a copy to Mr. Waugh.
p
STEVE INOTT
Mr. Inott waited to know if they needed a variance or subdivision
to deride a tea acre parcel into two five acre parcels. They were
told they would have to go through a subdivision because a road was
required. They were told to get a copy of the subdivision code and
contact Bill Schwab or Dennis Welch.
LEN NO ACK
Motion made by Spitzer, seconded by Johnson, recommending that this
Junk Yard Special Use Permit be granted with all the previous
conditions with the date of Item 3 be changed from June 30, 1973
to. September 1, 1971, and subject to the condition that Mr. Noack
file the proper application.
Members for: Peloquin, Johnson, Ehret, Schletty, Leroux and
Spitzer. Motion carried.
Motion made by Spitzer and seconded that the meeting be adjourned
at 10:50 P.M. Motion carried.
Marie Janse , Secretary
Hugo Planning Commission