Prepared by BKV Group, Commission No. 1164.06 15 <br />Phase 7: Second Floor Remodeling (~760 sf) <br />Remove and salvage hollow metal doorframes with sidelights from offices and infill with new wood <br />doors and gypsum board walls. Replace ceilings, window treatments, etc. in new dorm rooms. <br />Provide new beds, wardrobes, and nightstands. Selectively remove walls and ceilings at existing <br />restrooms and locker rooms. Demolish all toilets, urinals, showerheads, and lavatory faucets and <br />salvage remaining plumbing. Construct new walls and ceilings and run plumbing and electrical to new <br />locations. Provide new plumbing fixtures and tie into existing sanitary sewer. Provide new wood <br />doors, hollow metal frames, hardware, and signage. Finish out new restrooms and locker area with <br />porcelain tile and new toilet accessories Provide porcelain tile floors and walls throughout locker and <br />shower area. Provide upgraded light fixtures and HVAC for this part of the building. Relocate <br />sprinkler heads and existing lockers. <br />Hard Costs: $ 165,000 <br />Soft Costs: $ 24,000 <br />Project Contingency: $ 19,000 <br />TOTAL: $ 209,000 <br /> <br />Ph ase 8: Emergency Generator Replacement <br />Install new 100 kW natural gas emergency generator with sound enclosure north of the hose tower <br />to serve as full station backup. Provide new concrete pad and conduits into existing electrical room. <br />Provide new automatic transfer switch connected to existing electrical panels. Provide new generator <br />annunciator panel. Demolish existing generator on apparatus bay mezzanine and provide blank-off <br />at existing louver. <br />Hard Costs: $ 48,000 <br />Soft Costs: $ 10,000 <br />Project Contingency: $ 5,800 <br />TOTAL: $ 63,800 <br /> <br />