o No work on July 3 and July 4 for Holiday. <br />o Continued laying drain tile. <br />Work completed the week of August 21 – August 25 <br />o Completion of draintile installation <br />o Prep for concrete installation. <br />Work completed the week of August 28 – September 1 <br />o Finish pouring concrete sidewalk and patio for the picnic shelter. <br />o Prep for bench pads for concrete. <br />o Substantial completion of playground structure. <br />o Site grading. <br />Work scheduled for the week of September 4 – September 8 <br />o Labor Day – No work <br />o Soil correction under the water feature. <br />o Wiring for picnic shelter. <br />o Install final pieces of playground equipment <br />Work scheduled for the week of September 11- September 15 <br />o Subgrade preparation for the poured-in-place rubber surfacing (PIP surfacing <br />planned to begin September 18.