acquisition and relocation costs. In addition to these costs, the Cities of Maplewood,
<br /> Roseville, and Little Canada have also been pursuing the burying of the electric power
<br /> lines along the Rice Street Corridor. These costs are estimated at $575,000.00, bringing
<br /> the total estimated project cost to $27.545 million dollars. Table 1 below outlines the
<br /> estimated cost breakout of the construction improvements.
<br /> Table 1
<br /> -e
<br /> ~ •-e •
<br /> -e•e a -e e •
<br /> Street lm rovements 4~~~~~yh~
<br /> ~b~~~=4`1 r ~ ~ ~ -~a~.
<br /> v~~~~~~ ~
<br /> Storm Sewer Improvements ~ ~ „e„~:,
<br /> Sanitary Sewer Improvements v,~~~~~~ Ar.,,,_. ,=~"s„~~
<br /> Water Main Improvements x~~~~M~?~~~ ~ z
<br /> Interchange Improvements ~~=~~~;~~f ~~v~:~~,`~•.;,.,,, ~~~y;=
<br /> Bu Overhyye+ad Power y} y x
<br /> {..,,.y ~ ;Vl~ .$~4~t 4 t , ~,.5 ~:~~s, f"xfi,:
<br /> 7v f~y'r 3~y~t ~~~~~Ics~'Z,3k;
<br /> ~,M. N.~~`~... ~i. I ,w <r; t.. `,....x ,.hv, ,..v. .1 . ~.aYES't sr..cr.,,.xz:v .N
<br /> Right-of-Way/Easement Acquisition ~"~r~ ~ 3~
<br /> ~x~ ~a ~ ~a ~
<br /> Design and Administration rs~:~~~~f` ~~i~~° '"~<s`~;~~}?_
<br /> ~Ce/o~!n/s'tru~c~+ti~on ~A`~dmin~if~s(tration zy, ~~`'r~2'~,Q`~i
<br /> i_~Y.1~F1i~1~1 Y/f~Y~'~~+j~.",l lb,;.ar ~S~.G.i~' l.~ x :KS„"2~...~'SAF~1 ~ A..P „i~."~u~..:i.$rv,~.S.. 5
<br /> As stated previously the project is a multiple agency project including Mn/DOT, Ramsey
<br /> County, and the Cities of Little Canada, Maplewood, and Roseville. While the total
<br /> project costs are relevant to this report, the more important factor for the City of Little
<br /> Canada is what portion of the total project cost is expected to be the responsibility of the
<br /> City of Little Canada. At this time the City of Little Canada portion of the project cost is
<br /> estimated at $637,500.00. That amount includes all construction, design, and
<br /> construction administration costs for the project. The City typically adds an additional
<br /> 5% to the project cost to account for City overhead costs and the assessment process
<br /> associated with the project. Adding the 5% City overhead increases the overall project
<br /> cost to approximately $670,000.00. The County is still pursuing some additional funding
<br /> sources for the project and has indicated that if received those funds may be applied to
<br /> reduce the local community costs of the improvements.
<br />
<br /> XI. FINANCING
<br /> As stated above, the County is in the process of finalizing the funding sources for the
<br /> project which may include grants from Federal Surface Transportation (STP) funds and
<br /> the Department of Economic and Employment Development (DEED); Mn/DOT local
<br /> interchange, Trunk Highway Turnback, Bridge, and Cooperative Agreement funds; city
<br /> funds, and property owner assessments. Table 2 outlines the anticipated funding
<br /> sources for the project as a whole.