Laserfiche WebLink
2.6 Opening of construction bids for the Building project is planned to occur <br />in early February, 1989. Construction is planned to commence in mid March <br />1989. <br />2.7 Carley Engineering will study and prepare preliminary grading, paving, <br />landscaping and drainage plans for further discussion and consideration by <br />January 1, 1989. Carley Engineering anticipates completion of bidding and <br />construction documents no later than March 1, 1989. The architect asked <br />for the City to consider completing design and bidding at an earlier date <br />since coordination of construction timing and sequence between the School's <br />and the City's respective contractors is essential to achieving the August <br />18, 1989 project completion date. <br />Please advise immediately if any exception is taken to the above. <br />Sincerely, <br />BUETOW & ASSOCIATES, INC. <br />Randy L. Engel <br />Project Architect <br />cc: John Thein <br />Don Carley <br />David O'Connor <br />Page 6 <br />