Laserfiche WebLink
MINUTES <br />CITY COUNCIL <br />APRIL 9, 2014 <br />PUBLIC <br />WORKS - <br />PARKS <br />FACILITY <br />PROJECT <br />UPDATE <br />The City Administrator reported that the Council held a workshop meeting <br />earlier this evening to review the Public Works -Parks Garage project. The <br />Administrator reported that the estimated cost of the project has increased, <br />so the Council reviewed cost reduction options which were recommended <br />by the project committee. The Administrator noted that the City sold <br />bonds to finance the estimated project costs of $3.4 million, and project <br />estimates were approximately $900,000 over that amount. The project <br />committee recommended cost reductions in the amount of $372,000, and <br />the Council concurred at the workshop meeting with those reductions. <br />The Administrator reported that the project is still approximately $500,000 <br />over the $3.4 million bond issue. The Administrator pointed out that these <br />estimates include $225,000 in contingencies. He noted that the <br />Construction Manager has indicated that as schematic designs are <br />finalized and better estimates obtained, the contingency amount will <br />reduce. <br />The Administrator reviewed the cost reductions that were agreed to, some <br />of which include a reduced height on the building, the moving of the parks <br />shop into the mechanics bay, reduction in the square footage for the office <br />area and mezzanine, and building drainage changes. Again, these cuts <br />total $372,000, which leaves the project at $494,778 over budget. The <br />Administrator noted that the City had been prepared to fund a $2 million <br />project with cash -on -hand. He pointed out that the increase project costs <br />will not change water and sewer rates nor increase the City's tax levy if <br />we fund the additional amount from cash reserves. The Administrator also <br />pointed out that the Construction Manager has indicated that as the project <br />moves toward final design and bidding, project estimates should be within <br />1% to 2% of final costs. <br />Blesener indicated that as the project moves forward to the design stage, it <br />may be possible to identify more cost savings. Blesener agreed that the <br />Construction Manager suggested that within the next 4 to 6 weeks, the <br />City should have estimates to within 1% to 2% of final costs. <br />At this point in the meeting, the City Administrator compared the first <br />building plan with the revised plan that includes the cost reductions. He <br />noted that the exterior has a lower roof line and that the brick treatments <br />have been eliminated. The Administrator reviewed internal building <br />changes as discussed earlier. The Administrator stated that the design <br />committee does not feel changes proposed compromise the long -term <br />functionality of the building. <br />5 <br />