Watermain Repair:
<br />• Bolt replacement on identified gate valves and to check two water services on Forsham
<br />Lake Drive, Stage Coach Trail and Post Road.
<br />The Street Rehabilitation project included two alternative bids, in the event bid prices permitted
<br />additional work within budget:
<br />Alternate No. 1-
<br />Bituminous Overlay of Oak Lane and Knoll Drive.
<br />Alternate No. 2-
<br />Bituminous Overlay of James Street.
<br />Bids were received on Friday, January 29, 2021. A total of seven bids were received. As shown
<br />below:
<br />CONTRACTOR
<br />TOTAL
<br />BASE BID
<br />TOTAL
<br />BASE BID +
<br />ALT 1
<br />TOTAL
<br />BASE BID +
<br />ALT 2
<br />TOTAL
<br />(BASE BID +
<br />ALT 1 + ALT
<br />2)
<br />T.A. Schifsky & Sons,
<br />Inc.
<br />$1,997,794.23
<br />$2,112,930.23
<br />$2,064,869.23
<br />$2,180,005.23
<br />Valley Painting, Inc.
<br />$1,993,687.68
<br />$2,118,819.03
<br />$2,069,931.18
<br />$2,195,062.53
<br />North Valley, Inc.
<br />$2,113,725.57
<br />$2,231,271.48
<br />$2,183,961.94
<br />$2,301,507.85
<br />Forest Lake Contracting
<br />$2,324,517.70
<br />$2,475,256.82
<br />$2,419,483.94
<br />$2,570,223.06
<br />Northwest
<br />$2,335,879.65
<br />$2,488,288.69
<br />$2,429,667.30
<br />$2,582,076.34
<br />Park Construction Co.,
<br />Inc.
<br />$2,479,866.35
<br />$2,617,859.75
<br />$2,559,990.35
<br />$2,697,983.75
<br />Dresel Contracting
<br />$3,796,739.21
<br />$3,937,293.50
<br />$3,883,198.82
<br />$4,023,753.11
<br />The low bid was submitted by T.A. Schifsky & Sons, Inc. in the amount of $2,180,005.23 for
<br />the base bid and the bid alternates. Alternates 1 & 2, in the amounts of $115,136.00 and
<br />$67,075.00 respectively, are under the available budget and are being recommended for award.
<br />The total estimated project cost for the Street Reconstruction portion of the project, including
<br />soft costs and contingencies, is $1,800,000.00. This under the original $2,600,000.00
<br />authorized in the 2021-2024 Street Reconstruction Plan. This portion of the project will be
<br />funded through Street Reconstruction Bonds.
<br />The total estimated project cost for the Street Rehabilitation portion of the project, including
<br />soft costs and contingencies, is $823,000.00. This under the budget planned for 2021. This
<br />portion of the project will be funded through Pavement Management funds and the Water
<br />Operating fund.
<br />The completion date for this project is October 29, 2021.