Feasibility Study <br />Water Treatment Plant <br />City of Lino Lakes, MN <br />WSB Project No. 015822-000 Page 28 <br />9.1 Water Treatment Plant Financial Analysis <br />The estimated costs for the recommended gravity filtration water treatment plant option analyzed <br />in this report are summarized in Table 9-1 below and are broken out in greater detail in <br />Appendix E. The 20-year total costs include both the initial capital costs and the annual <br />operations and maintenance (O&M) costs for the first twenty years of plant operation. The capital <br />costs include a 10 percent construction contingency and 15 percent indirect costs (engineering, <br />legal, administrative, etc.). The annual operation and maintenance (O&M) costs are based on a <br />3.5 percent inflation rate. Funding this project through an adjustment to the City’s water rates, <br />water availability charge (WAC), or trunk watermain charges, or a combination that uses all of <br />these funding methods, should be evaluated as part of a detailed water utility rate study. <br />Table 9-1. Estimated Cost Summary for Water Treatment Plant <br />20-Year Capital Cost $20,032,155.40 <br />20-Year Loan Interest (1.5%)$3,303,597.25 <br />20-Year Operation and Maintenance Cost $3,323,438.80 <br />20-Year Total Cost Including Loan Interest $26,659,191.45 <br />9.2 Future Trunk Watermain Improvements Financial Analysis <br />The estimated costs for the Phase 1 trunk watermain improvements were not included in this <br />financial analysis because this project is already proceeding and being funded by other means. <br />The estimated costs for the future Phase 2, 3, and 4 trunk watermain improvements analyzed in <br />this report are summarized in Tables 9-2, 9-3, and 9-4 and are broken out in greater detail in <br />Appendix E. The capital costs include a 10 percent construction contingency and variable <br />indirect costs (engineering, legal, administrative, etc.) depending on the size of the project. <br />Funding these trunk watermain projects through an adjustment to the City’s trunk watermain <br />charge should be evaluated as part of a detailed water utility rate study. <br />Table 9-2. Estimated Cost Summary for Phase 2 Trunk Watermain Improvements <br />20-Year Capital Cost $178,571.25 <br />20-Year Loan Interest (1.5%)$29,449.03 <br />20-Year Total Cost Including Loan Interest $208,020.28 <br />Table 9-3. Estimated Cost Summary for Phase 3 Trunk Watermain Improvements <br />20-Year Capital Cost $1,646,346.90 <br />20-Year Loan Interest (1.5%)$271,506.83 <br />20-Year Total Cost Including Loan Interest $1,917,853.73 <br />Table 9-4. Estimated Cost Summary for Phase 4 Trunk Watermain Improvements <br />20-Year Capital Cost $3,921,500.00 <br />20-Year Loan Interest (1.5%)$646,713.06 <br />20-Year Total Cost Including Loan Interest $4,568,213.06 <br />9.3 Future Well Nos. 7 and 8 Raw Watermain Improvements Financial Analysis <br />Estimated costs for constructing raw water mains from future Well Nos. 7 and 8 are summarized <br />in Table 9-5 if the City decides to treat these wells at the water treatment plant versus pumping <br />them directly into the distribution system without treatment. These costs are broken out in greater <br />detail in Appendix E. The capital costs include a 10 percent construction contingency and 15 <br />percent indirect costs (engineering, legal, administrative, etc.). Funding these raw watermain improvements through an adjustment to the City's water rates, water availability charge (WAC), <br />or trunk watermain charges, or a combination that uses all of these funding methods, should be <br />evaluated as part of a detailed water utility rate study.