<br /> <br /> <br /> <br /> <br />DATE: March 6, 2023 <br /> <br />TO: Park Board Members <br /> <br />FROM: Rick DeGardner, Public Services Director <br /> <br />RE: Watermark Park Update <br /> <br /> <br />On December 12, 2022, the City Council approved the plans and specifications and authorized the <br />Advertisement for Bids. Eight bids were received and opened on February 7, 2023. <br /> <br />The low bid was submitted by Dimke Excavating, Inc. in the amount $668,265.30, and Dimke <br />Excavating, Inc. was awarded the construction contract via Resolution 23-15. The engineer’s <br />estimate was $929,912.55. WSB and Associates submitted a proposal to complete the <br />construction services in the amount of $93,454.00 and was approved via Resolution 23-16. <br /> <br />Funding has been identified through the Dedicated Parks Fund. <br /> <br />The completion date for this project is October 31, 2023. <br /> <br />The resolution to approve the contract for the Watermark Park Playground Equipment was tabled <br />at the February 13, 2023 City Council meeting. The City Council expressed interest in exploring the <br />concept of designing all future playgrounds to be 100% ADA accessible. This will be discussed <br />during the March 6 work session. <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />