Ms. Katie Larsen <br />07/28/2023 <br />Page 3 <br />Milestones Addition & Lil Explorers Childcare Center Engineering Review <br />4.(5/3/2023) The City of Lino Lakes does not allow roof drains to be connected <br />directly to storm sewer. Roof drains need to have a 6-inch air gap before <br />draining to the storm sewer. Applicant to provide detail on plans. <br />(5/19/23) Note of 6” gap added <br />5.(5/3/2023) Infiltration rate testing is needed to ensure sufficient infiltration <br />capacity is present in site soils. Double ring infiltrometer or modified Phillip- <br />Dunne testing is recommended to determine these rates. Testing must be <br />completed prior to final plat appro val. <br />(5/19/23) Testing is scheduled <br />(5/19/23) This comment remains open until testing results are provided. <br />6.(5/3/2023) Applicant to verify the constructability of CBMH-4. The pipes <br />proposed to come in at an acute angle may require a large diameter drainage <br />structure to ensure sufficient concrete is provided betwee n pipe openings. <br />(5/19/23) The CB will be sized as necessary <br />7.(5/3/2023) Applicant to provide riprap at the FES-5 inlet to the north infiltration <br />basin. <br />(5/19/23) Riprap added <br />8.(5/3/2023) Applicant to provide a bioroll weir at FES-5 for sediment control. <br />(5/19/23) added <br />9.(5/3/2023) Applicant to provide silt fence around FES-6 until final stabilization <br />has been achieved to minimize risk of sediment loading to City stormwater <br />infrastructure. <br />(5/19/23) added <br />10.(5/3/2023) Applicant to provide silt fence around infiltration basin s until final <br />stabilization has been achieved to maintain infiltration capacity. <br />(5/19/23) Compost logs will be added in lieu of silt fence because they function <br />better in this application and it avoids future impacts of silt fence removal. <br />11.(5/3/2023) Applicant to revise vegetated filter strip pretreatment for the south <br />infiltration basin in accordance with MN Stormwater Manual design standards. <br />This primarily entails providing a strip at l east 3-ft wide and with a slope of 2- <br />6% along the impervious areas flowing to the basin. <br />(5/19/23) Added strip <br />12.(5/3/2023) Applicant to provide a sump on CMBH-5 to provide pretreatment <br />prior to discharge to the north infiltration basin. <br />(5/19/23) Sump added <br />13.(5/3/2023) Modeled curve numbers of disturbed pervious areas must be <br />revised to account for the effects of soil compaction. Per City and Watershed <br />standards, B soil pervious areas must be revised to have a curve number of <br />74. <br />(5/19/23) revised <br />14.(5/3/2023) Please clarify the drainage areas map. Drainage areas 2.2 is <br />shown but not referenced anywhere else in the SWMP. Additionally, the scale <br />bar on the proposed conditions drainage area map is unclear. <br />(5/19/23) Removed 2.2 from map <br />15.(5/3/2023) Exfiltration cannot be included in the modeling of the proposed <br />basins in HydroCAD. <br />(5/19/23) Exfiltration removed. <br />16.(5/3/2023) The outlet pipe for the north infiltration basin must be updated to <br />reflect the inverts shown in the plans.