Laserfiche WebLink
Feasibility Report Section 6 - Project Schedule <br />The City Charter requires a period of sixty (60) days to elapse after the public hearing and <br />before any further action can be taken by the City Council on the proposed improvement. With <br />that in mind, the proposed project schedule is amended as follows: <br />Task Completion Date <br />Receive Report on Improvements Amended Feasibility Report ....................... December 11, 2017 <br />Neighborhood Meeting (60% Plan Completion) .................................................. January 11, 2018 <br />Public Improvement Hearing .............................................................................. January 22, 2018 <br />60-Day Petition Period Ends (City Charter) ............................................................ March 22, 2018 <br />Authorize Advertisement for Bids ................................................................................. April 2018 <br />Project Bidding .............................................................................................................. May 2018 <br />Set Assessment Hearing ................................................................................................. May 2018 <br />Assessment Hearing ...................................................................................................... June 2018 <br />Award of Bid ................................................................................................................... July 2018 <br />Begin Construction (Culvert, By-Pass for access, Utilities) ................................................ Fall 2018 <br />Begin Construction (Utilities and Street) ..................................................................... Spring 2019 <br />Completion of Construction and Restoration .................................................................. Fall 2019 <br /> <br />