Laserfiche WebLink
2 <br /> <br /> <br />Contractor Base Bid <br /> Allied Blacktop Company $110,464.00 <br />Corrective Asphalt Materials $191,109.00 <br /> <br />The low bid was submitted by Allied Blacktop Company in the base bid amount of $110,464.00 <br />which is within the planned budget and is being recommended for award. Allied Blacktop <br />Company successfully completed the City’s 2023 Crack Fill and Seal Coat Project. <br />The estimated total project cost including contingency and overhead is $140,000. The project is <br />funded through the Pavement Management Funds. <br />The substantial completion date which includes sweeping and site cleanup is August 2, 2024 and <br />the final completion date for this project is August 30, 2024. <br />RECOMMENDATION <br /> <br />Staff is recommending approval of Resolution No. 24-37, Accept Bids and Awarding a <br />Construction Contract for the 2024 Rejuvenator Project. <br /> <br />ATTACHMENTS <br /> <br />1. Resolution No. 24-37 <br />2. Project Location Map <br />3. Bid Summary <br /> <br /> <br />72