The estimated total project cost is $1,200,000.00. Funding for the project is expected to be <br />from the Pavement Management Fund, Storm Water Utility fund, and Water Operating Fund. <br />The project schedule: <br />Authorize Preparation of Plans and Specifications <br />October 14, 2024 <br />Order Improvement, Approve Plans and Specs, Authorize Ad for Bids <br />December 9, 2024 <br />City Opens Bids <br />February 4, 2025 <br />City Council Awards Contract <br />February 10, 2025 <br />Construction Begins <br />April -May, 2025 <br />Final Completion <br />August 30, 2025 <br />Staff is recommending approval of Resolution No. 24-160, Order Project, Approve the Plans and <br />Specifications and Authorize the Ad for Bid for the 2025 Street Rehabilitation Project. <br />ATTACHMENTS <br />1. Resolution No. 24-160 <br />2. Construction Plans <br />