Laserfiche WebLink
Table 6 <br />Lino Lakes WTP Feasibility Report <br />Cost Estimate for Raw Watermain to West Site <br />No Description Cost <br />1 8" HDPE Watermain (directionally drilled) 24,321 LF $ 851,235 <br />2 10" HDPE Watermain (directionally drilled) 2,052 LF $ 92,340 <br />3 16" HDPE Watermain (directionally drilled) 6,343 LF $ 475,725 <br />4 24" HDPE Watermain (directionally drilled) 2,757 LF $ 358,410 <br />5 Hydrant Assemblies 11 EA $ 49,500 <br />Construction Subtotal $ 1,827,210 <br />Construction Contingency $ 182,721 <br />Total Construction Cost $ 2,009,931 <br />Administration, Engineering and Financing $ 401,986 <br />*Total Capital Cost $ 2,411,917 <br />Final Estimated Cost $ 2,425,000 <br />* Cost does not include right of way acquisition or restoration. <br />Water Treatment Plant Study 18 13843.000 <br />