Table 7 <br />Lino Lakes WTP Feasibility Report <br />Cost Estimate for Raw Watermain to East Site <br />No. Description Cost <br />1 8" HDPE Watermain (directionally drilled) 24,321 LF $ 851,235 <br />2 10" HDPE Watermain (directionally drilled) 2,052 LF $ 92,340 <br />3 16" HDPE Watermain (directionally drilled) 906 LF $ 67,950 <br />4 24" HDPE Watermain (directionally drilled) 8,194 LF $ 1,065,220 <br />5 Hydrant Assemblies 11 EA $ 49,500 <br />Construction Subtotal $ 2,126,245 <br />Construction Contingency $ 212,625 <br />Total Construction Cost $ 2,338,870 <br />Administration, Engineering and Financing $ 467,774 <br />*Total Capital Cost $ 2,806,643 <br />Final Estimated Cost $ 2,800,000 <br />* Cost does not include right of way acquisition or restoration. <br />Water Treatment Plant Study 19 13843.000 <br />