• <br />Main Street Village <br />page 7 <br />The southern driveways from the gas station and the large retail site should be moved west <br />approximately 70' to avoid conflicts with the intersection of the slip lane road. This new <br />driveway location will allow for ample access to the gas pumps and the convenience store <br />and shouldn't cause parking or circulation problems on the south side lot. <br />• The PUD requirement is for an internal road to be a minimum of 26' (Sec 2, Subd.10, <br />B.6). This road narrows to a pavement width of 25' on the plan and must be corrected. <br />This will be an important circulation route for the development area, providing access to <br />the larger development area. <br />• This means we must know that the second access can be constructed. We do not yet have <br />sufficient geotechnical information (soil borings) to be confident that this `road' can be <br />built. This is the reason the application is still incomplete. The specific timing of the <br />construction of the second access in relation to the phasing of development on the site will <br />need to be established if the project is to be approved. However, it is vital to know up <br />front if the soils will support the access route. <br />Lino Lakes has a joint powers agreement with Anoka County that limits the number of <br />accesses that will be allowed on Otter Lake Road (Co. Rd. 84) between Main Street. and <br />Cedar Street. We can have a total of six driveways and three roads. There are five <br />driveways now and two roads. We would prefer to use the allocation wisely. We have <br />suggested that the new southern access on this development site be planned along the <br />property line with the City's water tower. This would allow the elimination of the <br />existing water tower driveway onto Otter Lake Road: the water tower driveway would be <br />on the new access `road'. This would save a driveway access and possibly provide a little <br />more usable land for the development site. <br />A traffic study was prepared for the development. The study considers the existing proposal <br />(phase one) and future development on the site. The study assumes the existing bank road <br />will be a full access point with phase one of the development, but be converted to right - <br />in/right -out only with full development. As to the southern access, it will function properly <br />with a stop sign with full development but will require a traffic signal by 2030 because of the <br />increasing background traffic. <br />The intersection of Otter Lake Road and Main St. will function well until 2030. The AUAR's <br />traffic analysis also recognized that this intersection will fail at that time. This is an important <br />transportation planning issue that will require the attention of both County and City. It likely <br />will require further improvements such as additional lanes on Main St. <br />The plan includes an addition five feet of right of way dedicated for Otter Lake Road as well <br />as a triangle for future needs at the Main St. intersection. However, this is shown only on the <br />northern portion of the site. The dedication must be shown on the southern part as well. <br />• The internal road leading to Otter Lake Road must be 26' in width. It is 30'+ on the east, but <br />only 25' on the west end. <br />