Laserfiche WebLink
writing the park has dried allowing a number of improvements to take place. Projects have <br />included: <br />Installation of play area curbing. <br />Backfill of play area curbing. <br />Seventy percent completion of landscape plantings. <br />Play structure delivered and stored on -site. <br />If the weather stays dry we are hoping to pour the gazebo footings and begin installing the smaller <br />Kid Time structure this week. The larger structure is now scheduled for June 8. (Please be dry!) <br />Those are May's major highlights. Much more to come in June. <br />sw /parkbrd/mike/May 02 Park Update.doc <br />• <br />• <br />