Project Schedule <br />It is necessary that the Lake Drive Trunk Utility Project is complete prior to <br />commencing with the Apollo Drive Project. The Lake Drive Trunk Utility Project <br />will not be complete in time to allow the Apollo Drive Project to start this year. <br />Therefore, construction is planned to start spring, 1999. The following table <br />summarizes the following steps and estimated dates to complete the project: <br />Order Improvement and Authorize <br />Preparation of Plans July 13, 1998 <br />Approve Plans and Specifications and <br />Authorize Advertisement for Bids August 10, 1998 <br />Approve Joint Powers Agreement August 10, 1998 <br />Open Bids January, 1999 <br />Receive Bids and Award Contract February, 1999 <br />Begin Construction May, 1999 <br />End Construction July, 1999 <br />Assessment Hearing September, 1999 <br />