Laserfiche WebLink
Mn/D€Y ?P- 2460 - 0112 -92) <br />SHEET 1 OF 2 SHEETS <br />State of Minnesota - Department of Transportation <br />CHANGE ORDER # 14 <br />contractor: Lunda Construction Co. <br />Address: 15601 Clayton Avenue S. <br />Rosemount, MN 55068 <br />State Project No.: 0280 -55 <br />Contract No. Z07502 <br />Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr. <br />In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions. <br />While starting to jack the casing necessary for the work identified in Change Order #7,it was determined that <br />the use of a 42" casing would come into conflict with the 35W pavement. It was therefore necessary for the <br />Contractor to use a smaller casing and different pipe materials. This change required the Contractor to reset <br />their pipe jacking equipment so that the proper grades can be established. As a result the Contractor has <br />claimed that there are costs associated with the initial installation of the 42" casing before the conflict was <br />discovered that are not addressed under the pipe jacking work on Change Order #7. The Engineer has reviewed <br />these claims and determined that some of the claims asserted are valid. <br />This Change Order provides settlement of all claims for the work involved with initially installing the 42" <br />casing. By signing this Change Order the Contractor also acknowledges that the remaining work required to <br />install the 36" casing and pipe will be performed as agreed in the previously issued Change Order #7. <br />*he Contractor will not make claim of any kind or character whatsoever for any other costs or expenses that he <br />may have incurred or that may be hereafter incurred in performing the work and furnishing the materials <br />required by this Change Order. <br />Payment to the Contractor will be at the lump sum negotiated price as full and final settlement of the claims <br />detailed above, as shown below in the Estimate of Cost. In addition, upon review of the steel casing, knuckle <br />and steering sensor, a credit will be applied to this Change Order at the negotiated prices shown below in the <br />Estimate of Prices if it is deemed that the materials can be salvaged by the Contractor. <br />ESTIMATE OF COST <br />Increase Negotiated Items <br />Item No. Description Unit Quantity Unit Price Amount <br />Pipe Jacking Claim Settlement L.S. 1 $13,816.14 $13,816.14 <br />Total Increase $13,816.14 <br />Decrease Negotiated Items <br />Item No. Description Unit Quantity Unit Price Amount <br />42" Steel Casing lin ft 21 $135.00 $2,835.00 <br />Knuckle each 1 $350.00 $350.00 <br />Steering Sensor each 1 $40.00 $40.00 <br />Total Decrease $3,225.00 <br />