CHANGE ORDER
<br />TOLTZ, KING, DUVALL, ANDERSON
<br />AND ASSOCIATES, INCORPORATED
<br />Engineers -Architects -Planners
<br />Saint Paul, MN December 9 19 99 Comm. No. 11494 Change Order No. 1
<br />To S. R. Weidema, Inc., 17600 113th Avenue North, Maple Grove, Minnesota 55369
<br />for Lilac Street Trunk Utility Improvements
<br />for City of Lino Lakes, Minnesota
<br />You are hereby directed to make the following change to your contract dated
<br />April 27 , 1998 . The change and the work affected thereby is
<br />subject to all contract stipulations and covenants. This Change Order will
<br />(increase) (dccrca c) (not changc) the contract sum by Fourteen Thousand Ninety
<br />Six Dollars and 00/100 ( $14,096.000 ).
<br />CHANGE ORDER No. 1
<br />This change order is for the complete construction of nine sanitary sewer services,
<br />as requested by the City's Park Department, located on the west side of Mustang
<br />Lane, at Stations 4+25, 5+50, 6+99, 7+79, 8+64, 9+37, 10+17, and 10+97, and the east
<br />side of Mustang Lane at Station 11+45. The work includes subcutting 700 LF of
<br />Mustang Lane for the installation of a Dewatering system, trench excavation for
<br />installation of the sanitary sewer services, installation of 4"x15" PVC wyes and 4"
<br />PVC SDR 26 sewer service pipe, trench and street subgrade restoration and removal of
<br />the dewatering system. This Change Order is also for furnishing and installing
<br />misc. culverts, 15" CMP and 24" culvert extensions:
<br />NET CHANGE =
<br />1) 4"x15" PVC SDR 35 Wye Branch, 4" PVC SDR 26 Service Pipe
<br />Complete in place, 9 Each @ $407/Each = $3,663.00
<br />2) Subcut 700 LF Mustang LN and Install Dewatering System, and
<br />restore trench & street subgrade @ $12/LF = $8,400
<br />3) F&I, 18" CMP Culvert, 1 @ $1,300
<br />4) Remove, Dispose of 15" CMP culvert, F&I 15" CMP culvert, 1 @ $283.00
<br />5) F&I, 24" culvert extension, 1 @ $450.00
<br />Amount of Original Contract
<br />$ 14,096.00
<br />$ 232,254.70
<br />Additions approved to date (Nos. ) $ 0.00
<br />Deductions approved to date (Nos.
<br />Contract amount to date
<br />Amount of this Change Order (Add)
<br />Revised Contract Amount
<br />Approved City of Lino Lakes, MN
<br />By
<br />$ 0.00
<br />$ 232,254.70
<br />$ 14,096.00
<br />$ 246,350.70
<br />TOLTZ, KING, DUVALL, ANDERSON
<br />Owner AND ASSOCIATES, INCORPORATED
<br />Approved _ S. R. Weidema, Inc.
<br />By
<br />Paul T. Hornby, P.E.
<br />White - Owner
<br />Contractor Pink - Contractor
<br />Blue - TKDA
<br />
|