Section 01 32 26 <br />CONSTRUCTION PROGRESS REPORTING <br />PART 1 - GENERAL <br />1.01 Description: <br />A. To provide a continuous record of the progress of the work, each Contractor shall <br />keep a daily progress report. <br />B. Format of progress reports shall be approved by Architect/Engineer at the pre - <br />construction meeting. <br />1.02 Quality Assurance: <br />A. Progress reports are to be filled out on a daily basis by the Contractor's job site <br />representative, who shall be in a supervisory position. <br />B. Wherever possible, reports shall be completed by the same individual throughout <br />the duration of the project. <br />1.03 The Architect/Engineer Shall Receive One (1) Copy of All Progress Reports on a <br />Weekly Basis. <br />PART 2 - NOT USED <br />PART 3 - EXECUTION <br />3.01 Completion of Progress Report: <br />A. Contractor shall complete one (1) form for each working day. <br />B. Forms shall also be completed for the following days: <br />1. Work days canceled or shortened due to weather, material shortages, or <br />labor conditions. <br />2. Holidays. <br />3.02 Forms Shall Be Legibly Filled out in Ink and All Pertinent Items Completed. <br />- END OF SECTION - <br />City of Lino Lakes <br />Lino Lakes Fire Station #1 <br />RSI Project #15-12120-02 <br />Construction Progress Reporting <br />01 32 26-1 <br />