PART 3 - EXECUTION <br />3.01 Construction Schedule: <br />A. As soon as practical after receipt of notice to proceed, complete the construction <br />analysis described in articles 2.1 above, in preliminary form. Meet with the <br />Architect/Engineer, review contents of proposed construction schedule, and make <br />all revisions agreed upon. Submit in accordance with paragraph 1.3 (B) above. <br />3.02 Periodic Reports: <br />A. Construction Schedule Contents: <br />1. Show activities or portions of activities completed during the reporting <br />period. <br />2. State the percentage of work actually completed and scheduled as of the <br />report date, and the progress relative to days ahead of, or behind the <br />allowable dates. <br />3. If work is behind schedule, provide a narrative report which shows, but is <br />not necessarily limited to: <br />a. A description of the problem areas, current and anticipated. <br />b. Delaying factors and their impact. <br />c. An explanation of corrective actions taken or proposed. <br />3.03 Revisions: <br />A. Make only those revisions to construction schedule as are approved in advance by <br />the Architect/Engineer. <br />- END OF SECTION - <br />City of Lino Lakes <br />Lino Lakes Fire Station #1 <br />RSI Project #15-12120-02 <br />Construction Progress Schedule <br />01 32 16-3 <br />