Laserfiche WebLink
WS — Item 6 <br />WORK SESSION STAFF REPORT <br />Work Session Item No. 6 <br />Date: March 7, 2016 <br />To: City Council <br />From: Michael Grochala, Community Development Director <br />Re: 2015 Mill and Overlay Project <br />Background <br />The 2015 Mill and Overlay Project was authorized by the City Council on February 23, 2015 as <br />part of the City's annual pavement management program. <br />The project was originally designed with a Base Bid and two alternatives. The intent behind <br />the bidding strategy was to potentially take advantage of aggressive contractor pricing and <br />optimizing the City's construction program (matching the construction phasing to the <br />programmed budget). In other words, if the contractor's bid came in high, we would not award <br />the bid alternative and postpone their construction until 2016. If the contractor's bid was low, <br />then we could expand the project scope to include the entire neighborhood. <br />The programmed project budget for the 2015 Mill and Overlay Project was $850,000. Based <br />on the bids that were received, it was recommended to award the complete program (base and <br />both alternatives) to Valley Paving in the amount of $668,676.92. This was believed to be the <br />best decision at the time because we were within the City budget and the entire neighborhood <br />would be completed with a single construction season. In August of 2015 the City Council <br />accepted a quote from Valley Paving in the amount of $55,905, to include replacement of <br />roadway culverts within the project area. This increased the total construction contract to <br />$724,582. The total project cost, with construction and engineering, was $813,000. <br />During the construction operation, it was discovered that there was an error in the estimated <br />bituminous material quantities established in the bidding documents (the quantities were <br />underestimated by WSB). Upon becoming aware of this issue WSB informed staff and the <br />item was discussed at the September 28, 2015 City Council work session. WSB provided an <br />additional cost of $175,000 based on the adjusted quantities. Two options were discussed with <br />the City Council: <br />Option 1, stay within the existing programmed budget by reducing the scope of the 2015 <br />project and complete the remaining neighborhood as part of the 2016 Overlay project; or <br />Option 2, complete the entire project in 2015 thereby exceeding the original programmed <br />budget for 2015. <br />