Table 1: Reclamation Costs <br />59th Street Court Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unit <br />Assessed Rate <br />Street Improvements $437,000 $305,250 $7,750 for 17 units <br /> <br />• Extension of City Water is feasible and requires full road reconstruction <br />o Extension of drinking water would be open cut with services extended to each property. <br />o The roadway will need to be fully reconstructed with a new sand and gravel base. <br />o Existing and proposed roadway is 24-feet wide (face of curb to face of curb). <br />o An extension of the existing storm sewer system is recommended. <br />o Barrier concrete curb (high back) is recommended along the length of the road. <br /> <br />• Table 2: Watermain and Street Reconstruction Costs <br />59th Street Court Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unit <br />Assessed Rate <br />Street Improvements $958,000 $670,700 $16,900 for 17 units <br />Watermain Extension* $340,000 $0 $21,250 for 16 units <br />*Costs cover watermain installed in the right-of-way. Connection fees and cost to extend water to the home <br />on private property is in addition to the assessed amount. <br />A property owner meeting was held on January 28, 2025 and had a number of property owners in <br />attendance. The information above was provided to those present on the call and uploaded to the project <br />website for reference. At the time this Staff report was submitted there has been no formal comment <br />received from any property owners. <br />Staff recommends reclamation of the existing road without extension of city water. <br />55th Street North: Preliminary Design Findings <br />• Geotechnical Investigation supports the reclamation of the existing roadway if watermain is not <br />extended. <br />o An extension of the existing storm sewer system is recommended. <br />o Existing and proposed roadway is 28-feet wide (face of curb to face of curb) <br />o Barrier concrete curb (high back) is recommended along the length of the road. <br />Table 1: Reclamation Costs <br />55th Street North Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unit <br />Assessed Rate <br />Street Improvements $408,000 $285,350 $22,300 for 5 units <br />$11,150 @ 50% for 1 unit <br /> <br />• Extension of City Water is feasible and requires full road reconstruction <br />o Extension of drinking water would be open cut with services extended to each property. <br />o The roadway will need to be fully reconstructed with a new sand and gravel base. <br />o An extension of the existing storm sewer system is recommended <br />o Existing and proposed roadway is 28-feet wide (face of curb to face of curb) <br />o Barrier concrete curb is recommended along the length of the road.