Laserfiche WebLink
<br />• Table 2: Watermain and Street Reconstruction Costs <br />55th Street North Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unity <br />Assessed Rate <br />Street Improvements $821,000 $574,600 $44,800 for 5 units <br />$22,400 @50% for 1 unit <br />Watermain Extension* $230,000 $0 $46,000 for 5 units <br />*Costs cover watermain installed in the right-of-way. Connection fees and cost to extend water to the home <br />on private property is in addition to the assessed amount. <br />A property owner meeting was held on January 28, 2025 and no property owners attended. The information <br />above was uploaded to the project website for reference. At the time this Staff report was submitted there <br />has been engagement from any property owners. <br />Staff recommends reclamation of the existing road without extension of city water. <br />Irish Court North: Preliminary Design Findings <br />• Geotechnical Investigation supports reclamation of the existing roadway if watermain is not <br />extended. <br />o Storm sewer repairs are recommended <br />o Existing and proposed roadway is 32-feet wide (face of curb to face of curb). <br />o Barrier concrete curb and gutter is recommended along the length of the roadway. <br />Table 1: Reclamation Costs <br />Irish Court North Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unit <br />Assessed Rate <br />Street Improvements $248,000 $173,100 $10,700 for 7 units <br /> <br />• Extension of City Water is feasible and requires full road reconstruction <br />o Extension of drinking water would be open cut with services extended to each property. <br />o The roadway will need to be fully reconstructed with a new sand and gravel base. <br />o Existing and proposed roadway is 32-feet wide (face of curb to face of curb). <br />o Storm sewer repairs are recommended <br />o Barrier concrete curb and gutter is recommended along the length of the roadway. <br /> <br />• Table 2: Watermain and Street Reconstruction Costs <br />Irish Court North Total Estimated <br />Project Costs <br />City Share of Project <br />Cost <br />Estimated Per Unity <br />Assessed Rate <br />Street Improvements $585,000 $409,300 $25,100 for 7 units <br /> <br />Watermain Extension* $144,200 $0 $20,600 for 7 units <br />*Costs cover watermain installed in the right-of-way. Connection fees and cost to extend water to the home <br />on private property is in addition to the assessed amount. <br />A property owner meeting was held on January 28, 2025 and two property owners attended. The <br />information above was uploaded to the project website for reference. At the time this Staff report was