Project Schedule <br />JUNE 3, 2025 Council authorizes preliminary design, geotechnical services, and Orders Feasibility Report. <br />AUGUST 13, 2025 Neighborhood Meeting on Scope of Improvements. <br />SEPTEMBER 16, 2025 Presentation of Feasibility Report and Preliminary Design. <br />Council accepts Report and calls for Hearing on Improvement. <br />OCTOBER 21, 2025 Public Improvement Hearing. Council Orders the Improvement and authorizes preparation of <br />Plans and Specifications. <br />JANUARY 6, 2026 Council approves Plans and Specifications and orders. Advertisement for Bids is authorized. <br />FEBRUARY 5, 2026 Project Bid Date: Receive Contractor Bids <br />FEBRUARY 17, 2026 Council Accepts Bids and Awards Contract. <br />MARCH, 2026 Conduct Pre -Construction Meeting and Issue Notice to Proceed. <br />•AUGUST 28, 2026 Substantial Completion <br />•OCTOBER 16, 2026 Final Completion <br />*Final Assessment Hearing Schedule TBD