LAUNCH-CROSSROADS Time of Performance: December 31, 2022
<br />DEVELOPMENT AGREEMENT AMOUNTS
<br />CATEGORY CONSTRUCTION 125%REMARKS #1 #2 #3 #4 #5 #6
<br />Grading $468,200 $585,250 100%$585,250
<br />Sanitary Sewer $489,910 $612,388 75%$459,291
<br />Watermain $314,777 $393,471 75%$295,103
<br />Storm Sewer (w/pond structures)$167,791 $209,739 100%$157,304 $52,435
<br />Streets + Sidewalks $834,438 $1,043,048 100%$782,286 $260,762
<br />Bituminous Trails $31,896 $39,870 100%$29,903 $9,968
<br />Surface Water Facilities $57,050 $71,313 100%$53,484 $17,828
<br />Street Lighting NA NA
<br />Street and Traffic Signs $8,720 $10,900 100%$8,175 $2,725
<br />Private Utilities (electricity, gas, etc.)NA NA
<br />Landscaping $343,645 $429,556 $322,167
<br />Tree Preservation and Restoration NA NA
<br />Wetland Mitigation and Buffers NA NA
<br />Monuments NA NA
<br />Erosion Control $46,925 $58,656 100%$43,992 $14,664
<br />Record Drawings $5,250 $6,563 100%$4,922 $1,641
<br />TOTALS $2,768,602 $3,460,753 RELEASED AMOUNTS:$2,419,710 $360,022 $322,167 $0 $0 $0
<br />CUMULATIVE AMOUNTS:$2,419,710 $2,779,732 $3,101,899
<br />SECURITY AMOUNT REMAINING:$1,041,043 $681,021 $358,854
<br />DATE:1/2/2024 1/7/2025 6/17/2025
<br />REDUCTIONS
|