<br /> <br />Estimated Project Timeline – Phase 1 (2026) <br />Phase 1 - City Owned 180-acres Ideal & Stillwater Blvd <br />Item Date Notes <br />CC Workshop 3/10/2026 <br />Begin Engineering Planning of Sewer Connection March/April <br />County Coordination March/April Work with WA County to discuss access and <br />future projects near site <br />Hiring Broker April <br />Hire Broker to provide Broker Price Opinion on <br />Parcel 1 and field interest in the property; <br />research and find pricing and bring back <br />recommendation <br />AUAR Spring-Fall Work with consultants to renew AUAR on site <br />Public Engagement Process April - August <br />Survey April <br />Town Hall April/May <br />PH at EDA June <br />Begin sewer work June to Parcel2 and 3 <br />Marketing of Parcel 1 Late <br />Summer/Fall <br />Land Use& Zoning updates tbd Dependent on feedback and interest in property <br />