110 <br /> PEDESTRIAN BRIDGE WORK PLAN <br /> PROJECT COMPONENT RESPONSIBLE STAFF TIMELINE <br /> Task Force Mtg. #1 - to Saarion/BRW Feb.6, 1996 <br /> discuss use patterns and design <br /> components. <br /> Gain Paster's position Cathy Bennett March 20 -29 <br /> Discuss negiotions options for <br /> Paster Enterprise easement Cathy Bennett April Worksession <br /> Storm Water Drainage SEE/Ulrich By April , 1996 <br /> Pond Engineering/Permits/Info <br /> Pedestrian Bridge Design Review Task Force Mtg T2 May, 1996 <br /> SaarioniBRW <br /> 0 <br /> Obtain Easements BRW, Pruitt/Whiting./ By July, 1996 <br /> Bennett _ _ - _ . .--- ... <br /> Apt rove BRW's Design Plans SEH July, 1996 <br /> Approve Bridge Design City Council " JuIy, 1996 <br /> Specifications/Bid Award IMNDOTiBRW September, 1996 <br /> Construction Bid Award Co./BRW Spring, 1997 <br /> Tandom the Storm Pond work Bid Award Co./Liric:JSEH Spring, 1997 <br /> Construction Completion BRW/Const.Co. . August, 1997 <br /> nun Paperwork ---~,. Saarion November, 1997 <br /> • <br /> It is our aim to complete the pedestrian bridge project as soon as possible. Because of outside <br /> unknown factors including Federal.plan review., obtaining easements and negotiations with Paster <br /> ioEnterprises, NLvJDOT timelines for specifications, bidding and award, and construction company <br /> workloads, the timeline may change. <br />