Bond Counsel for the Issuance of General Obligation Capital Improvement Plan Bonds
<br />for Financing the Construction of a Public Works Facility.
<br />• January 9, 2017, Approved Resolution 8696, Resolution to Approve Plans and
<br />Specifications for Public Works Facility and Authorize Advertisement for Bids
<br />
<br />The project was advertised in the Sun Focus starting on January 20, 2017, and it ran in four
<br />consecutive papers through February 10, 2017. In addition, the plans and specifications were
<br />available at Oertel Architects, the Minnesota Builders Exchange, Dodge Data Analytics, CMD
<br />Construction Market Data, Blue Book and on the City of Mounds View’s website. On January
<br />25, 2017 there was a mandatory pre-bid conference that was attended by 25 general
<br />contractors and subcontractors.
<br />
<br />The bid opening was held on February 21, 2017 in the City Council Chambers. There were 12
<br />bids received. As part of the bidding process there were five Addendum issued that clarified
<br />questions asked of the architect and provided additional information regarding the project. The
<br />most critical of these provided the contractors with knowledge that the Public Works staff would
<br />be vacating the building. This allowed the contractors to plan for demolishing the entire building
<br />and not providing any temporary enclosures. The following table provides the bidders names,
<br />base bids, alternate bids and unit prices.
<br />
<br />During the bidding process, there were four alternate bid items along with a unit price request
<br />for three items. Bid alternates allow either reduction of work to reduce cost of the building or
<br />addition of work that is not critical to the operation of the building. Alternate 1 is additive for
<br />painting the vehicle storage area walls. Alternate 2 is additive for providing concrete storage
<br />panels for the bulk material storage area. Alternate 3 is deductive for reducing the vehicle
<br />storage area by 20 feet in length. Alternate 4 is deductive for reducing the size of the cold
<br />storage area by approximately 21 feet in length. Unit prices are for various smaller items of
<br />work that can be added (typically in minimum amounts) to the project that provide better
<br />functionality or aesthetics. Unit price number 1 is for each additional skylight and the minimum
<br />order is 4 units. Unit price number 2 is for each additional section of decorative screen wall
<br />fencing, and the minimum order is for 12 sections, each 4 feet in length. Unit price number 3 is
<br />for asphalt paving per square yard, and the minimum order is 20 square yards.
<br />
<br />The current project estimate is presented below along with the bid cost for the construction and
<br />other items needed to complete the project. The Final Project Estimate is $6,900,198, and the
<br />As Bid cost is $6,207,196. The bid price is shown to the right of the final project estimate. The
<br />Base Bid for the low bidder is well below the estimate and staff is recommending that alternates
<br />1 and 2 be awarded with the contract.
<br />Contractor Base Bid Alt. 1 Alt. 2 Alt. 3 Alt. 4 Unit Price 1 Unit Price 2 Unit Price 3
<br />Ebert Construction 5,156,000$ 21,910$ 31,949$ (58,925)$ (41,623)$ 2,500$ 700$ 21$
<br />Jorgenson Construction 5,199,000$ 23,000$ 33,000$ (71,000)$ (28,000)$ 4,500$ 665$ 23$
<br />ProjectOne Construction 5,234,995$ 23,400$ 34,118$ (62,909)$ (31,890)$ 2,650$ 750$ 25$
<br />Kue Contractors 5,290,431$ 24,000$ 55,000$ (84,000)$ (42,000)$ 2,800$ 750$ 24$
<br />W. Gohman Construction 5,358,466$ 8,900$ 35,000$ (54,000)$ (31,800)$ 3,500$ 603$ 20.58$
<br />Rochon Corporation 5,364,000$ 24,000$ 34,000$ (32,000)$ (46,000)$ 3,500$ 650$ 40$
<br />Versacon 5,446,001$ 9,435$ 33,615$ (48,704)$ (36,163)$ 3,002.40$ 734.40$ 22.14$
<br />Tarraf Construction 5,555,000$ 22,000$ 33,000$ (56,000)$ (36,000)$ 3,200$ 900$ 21$
<br />Morcon Construction 5,570,000$ 8,800$ 35,000$ (50,000)$ (34,000)$ 6,500$ 800$ 65$
<br />Terra General Contractors 5,660,000$ 22,300$ 32,600$ (44,000)$ (34,000)$ 3,000$ 650$ 21$
<br />Weber, Inc.5,676,000$ 9,300$ 34,100$ (39,100)$ (36,600)$ 3,280$ 633$ 22$
<br />Ram General Contracting 5,870,000$ 7,095$ 34,700$ (75,600)$ (59,000)$ 2,950$ 664$ 21.70$
<br />Public Works Facility Bids along with Bid Alternates and Unit Prices
|