Change Orders 20 through 26 are consistent with the projected change order <br />summary included in the March 13, 2006 Staff report. The total amount of all <br />change orders for this project has been reduced from the amount given in the <br />March 13, 2006 Staff report of $94,751.00, to the new estimated amount of <br />$93,570.00 <br /> <br /> <br />The following is a summary of the estimated final cost of this project: <br /> <br />City Hall Rehabilitation Cost Items <br />Construction Contract $1,185,000 <br />Construction Services $46,000 <br />Change Orders $93,570 <br />Grading Contractor $5,500 <br />Vegetation Establishment / Landscape Contractor $7,500 <br />Part time / Temporary employee (did not do –was $5800) $0 <br />Re-Settlement Work $6,000 <br />Furniture Budget $61,525 <br />Furniture contract adjustment 2/27/2006 $2,104 <br />Furniture contract adjustment 6/12/2006 $X,XXX <br />Moving contractor $20,000 <br />Police Office Space Rental $0 <br />Storage Shelving $8,800 <br />Interior Decorations / Pictures $3,000 <br />Window Treatments $7,400 <br />Community Center Rental $40,000 <br />Estimated Total $1,486,400 <br /> <br /> <br />Recommendation: <br />It is recommended the Council adopt the attached resolution approving Change <br />Orders No. 20 through 26 for the City Hall Rehabilitation Project. <br /> <br /> <br />Respectfully Submitted, <br /> <br /> <br /> <br />Greg Lee, Director of Public Works <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />