<br />The options are summarized as follows: <br /> <br />Option 1 – Do Not Award a Contract <br /> <br />Option 2 - $149,877.50 construction cost / $187,350 estimated project cost <br />Award the contract for just the Base Bid - segment from Edgewood Drive to <br />Knollwood Drive <br /> <br />Option 3 - $383,914.60 construction cost / $480,000 estimated project cost <br />Award the contract for Base Bid and the Alternate – entire segment, from <br />Edgewood Drive to West City Limits <br /> <br />Option 4 - $257,000 construction cost / $322,000 estimated project cost <br />Award the contract for just the segment from Edgewood Drive to Knollwood <br />Drive. Add in the segment from Knollwood Drive to the West City Limits as a <br />change order but delete the portion where the sidewalk crosses Spring Creek. <br /> <br />The County Road H Sidewalk Project will be financed utilizing Tax Increment <br />Financing (TIF). <br /> <br /> <br />Recommendation: <br />It is recommended the Council adopt the attached resolution awarding the <br />construction contract based on the (Base or Total) bid of Ti-Zack Concrete <br />Incorporated in the amount of ($149,877.50 or $383,914.6) for the County Road <br />H Sidewalk. <br /> <br /> <br />Respectfully Submitted, <br /> <br /> <br /> <br />Greg Lee, Director of Public Works Reviewed by City Administrator:___ <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />