2020 Street Project Staff Report Cont'd <br />The plans and specifications included two alternates for the reconstruction project. The <br />cost of Alternate 1 is $37,857.60, full curb replacement on the West side of Quincy Street, <br />and the cost for alternate 2 is $5,488.20 for sod replacement. The current specification <br />calls for hydro seeding in place of sod replacement. Past projects have resulted to <br />satisfactory or fair results in sod replacement. The majority of this project has established <br />lawns and installing new sod in shaded areas will results in less than favorable results. <br />If the City Council approves both Alternates the total reconstruction cost would be <br />$1,169,950.78. The break down on the cost and funding for the project are as follows: <br />Street Reconstruction of Quincy Street: <br />Street Reconstruction of Sherwood: <br />Quincy Street Private Improvement: <br />CIPP (Cured in place pipe) on Quincy: <br />Quincy Water Hydrant replacement: <br />Storm Sewer Pipe Replacement: <br />Sub Total <br />Bid Alternate 1: <br />Bid Alternate 2: <br />Total Re -Construction <br />$ 701,241.46 <br />fund account 430-4650-7050 <br />$ 45,659.24 <br />fund account 430-4650-7050 <br />$ 45,610.93 <br />fund account 430-4650-7050 <br />$ 128,285.93 <br />fund account 730-4823-7050 <br />$ 24,325.00 <br />fund account 700-4823-7050 <br />$ 179,248.22 <br />fund account 745-4415-7050 <br />$1,126,604.98 <br />$37,857.60 fund account 430-4650-7050 <br />$5A88-20 fund account 430-4650-7050 <br />$1,169,950.78 <br />Stantec has provided a fee estimate to provide engineering services for the construction <br />phase of this project. Those services include administration assistance, engineering, <br />inspection support, surveying and close out for this project. Compensation will be based <br />on the actual hours required plus reimbursable expenses for a maximum estimated fee <br />of $41,100.00. <br />American Engineering Testing, Inc. (AET) has provided a fee estimate to provide testing <br />engineering services during the construction phase of the project. Compensation will be <br />based on the actual hours required plus reimbursable expenses for a maximum estimated <br />fee of $19,603.75. <br />Strategic Plan Strategy/Goal: Maintain and Plan for Infrastructure Improvements. <br />Financial Impact: A budget adjustment in the 2020 Special Project Fund, account 480- <br />4180-7050 is needed for this project. The 2020 budget has $700,000.00. <br />