Mr. Don Peterson <br />City of Mounds View <br />Re: Recommendation for Notice of Award <br />Mounds View WTP No. 1 Rehabilitation <br />City of Mounds View <br />Mounds View, Minnesota <br />April 5, 2021 <br />Page 2 of 3 <br />chemical room equipment replacement, rooftop exhaust fan replacement, and boiler <br />system replacement. <br />In addition to the work to be completed at WTP No. 1, work at Wellhouse No. 1 includes <br />full electrical, lighting, control panel, PLC, radio, and OIT replacement. This includes the <br />addition of a VFD to Well No. 1. Contract No. 2 also includes lighting, control panel, PLC, <br />radio, and OIT replacement at Wellhouse No. 2. Process improvements include select <br />piping, valve, instrument, and appurtenances replacement for both Wellhouse No. 1 and <br />Wellhouse No. 2. Water Tower improvements include the addition of a pressure <br />transducer and control panel to monitor system pressure and tower access. <br />Alternate 1 — Wellhouse 1 and Wellhouse 2 Ventilation Improvements: <br />Mechanical and electrical related construction of air conditioning systems within existing <br />Wellhouse 1 and Wellhouse 2 to provide improved ventilation in these facilities with the <br />presence of Variable Frequency Drives (VFDs) for the well motors. <br />Alternate 2 — WTP No. 1 Pressure Vessel Hatch Replacement: <br />Replacement of one (1) 12" x 16" manway on each pressure filter with 24" diameter <br />manways. All furnishing, cutting, welding, installation, and recoating costs associated <br />with hatch replacement are incidental. <br />The attached Bid Tabulation presents a comparison of the apparent low bid to the Engineer's <br />Opinion of Total Probable Cost for the project, which was $1,981,500, which included a 10% <br />contingency. Bids were received from three (3) contractors including American Liberty <br />Construction, Inc. from Rockford, MN, Rice Lake Construction Group from Deerwood, MN, and <br />Municipal Builders, Inc. from Nowthen, MN. <br />Five (5) General Contractors attended the mandatory Pre -Bid meeting, of which, three (3) <br />responded to the bid opening. All General Contractors that attended could provide a quality <br />product. The City of Mounds View and AE2S did receive a Bidder Qualification form Municipal <br />Builders, Inc. who is the apparent low bidder within 24 hours after the bid and feel that they are <br />qualified to complete the work. The bidder qualification form is attached for reference. <br />Based on a review of the bids received, pending the City of Mounds View acceptance of the <br />contract price, and upon all local funding being secured, Advanced Engineering and <br />Environmental Services, LLC. (AE2S) recommends that the City of Mounds View award the <br />Base Bid construction contract and Alternate No. 1 and Alternate No. 2 to Municipal Builders, <br />Inc. of Nowthen, Minnesota. Municipal Builders, Inc. was the lowest responsive and responsible <br />bidder for a total construction cost (Base Bid Plus Alternate No. 1 and Alternate No. 2) of <br />$1,827,000. <br />Advanced Engineering and Environmental Services, LLC <br />6901 East Fish Lake Road, Suite 184 • Water Tower Place Business Center • Maple Grove, MN 55369 • 763-463-5036 <br />