RESOLUTION NO. 9561
<br />CITY OF MOUNDS VIEW
<br />COUNTY OF RAMSEY
<br />STATE OF MINNESOTA
<br />AWARDING A CONSTRUCTION CONTRACT
<br />TO T. A. SCHIFSKY & SONS FOR THE 2022 & 2023 STREET RECONSTRUCTION
<br />PROJECT OF SPRING LAKE ROAD AND PLEASANT VIEW DRIVE
<br />WHEREAS, the City of Mounds View is considering to rehabilitate Spring Lake
<br />Road from County Road J to County Road H2 and Pleasant View Drive North of Mounds
<br />View Boulevard to 84th Avenue NE; and
<br />WHEREAS, this project will include pavement rehabilitation and drainage
<br />improvements; and,
<br />WHEREAS, the City Council has approved the plans and specifications and
<br />authorized the advertisement for bid resolution; and,
<br />WHEREAS, this project was advertised a minimum of 21 days as required; and,
<br />WHEREAS, pursuant to an advertisement for City Project 2021 C-03 the
<br />2022/223 Street Rehabilitation Project, bids were received, opened and tabulated
<br />according to the law, and the following bids were received complying with the
<br />advertisement:
<br />Contractor
<br />Total Base Bid
<br />Alt Bid No. 1
<br />Alt Bid No. 2
<br />Alt Bid No. 3
<br />Alt Bid No. 4
<br />Low
<br />T. A. Schifsky &
<br />$3,579,081.45
<br />$70,202.00
<br />$40,949.00
<br />$51,861.50
<br />$32,203.50
<br />Sons
<br />#2
<br />North Valley,
<br />$3,733,073.10
<br />$52,249.72
<br />$30,221.53
<br />$40,370.68
<br />$34,112.40
<br />Inc
<br />#3
<br />Park
<br />$3,991,677.43
<br />$69,440.10
<br />$41,573.90
<br />$55,807.80
<br />$31,900.00
<br />Construction
<br />Co
<br />#4
<br />Douglass Kerr
<br />$4,115,044.19
<br />$61,230.55
<br />$33,749.45
<br />$45,174.70
<br />$32,970.00
<br />Underground,
<br />LLC
<br />#5
<br />New Look
<br />$4,153,450.70
<br />$62,991.00
<br />$34,914.00
<br />$46,814.00
<br />$35,000.00
<br />Contracting
<br />#6
<br />S.M. Hentges
<br />$4,265,004.65
<br />$62,189.50
<br />$32,845.50
<br />$44,040.50
<br />$31,600.00
<br />& Sons
<br />#7
<br />Bituminous
<br />$4,439,067.10
<br />$61,120.00
<br />$32,280.00
<br />$43,280.00
<br />$32,000.00
<br />Roadways Inc
<br />#8
<br />Forest Lake
<br />$4,533,620.00
<br />$84,147.00
<br />$44,443.00
<br />$60,223.00
<br />$30,000.00
<br />Contracting,
<br />Inc
<br />
|