<br /> <br /> <br />A draft Capital Improvement Program (CIP) has been developed for this program. It shows: <br />Segments 9-10, Long Lake Road to Silver Lake Road on the south side being constructed in 2006 <br />Segments 1-5, County Road H to Silver Lake Road on the north side being constructed in 2008 <br />Segment 6, Silver Lake Road to Pleasant View Drive on the north side being constructed in 2009 <br />Segments 7-8, Pleasant View Drive to Silver Lake Road on the south side being constructed in 2010 <br />Segment 11, Edgewood Drive to Woodale Drive on the south side being constructed in 2011(this segment will most likely be more dependent on re-development rather than a set time frame) <br /> <br />The Draft CIP was presented to the City Council on April 3, 2006. The City Council recommended that the City should seek to construct trailway segments 1-5 in 2007 utilizing City Funds <br /> and seek to be reimbursed with the federal grant funds at a later date when they become available. The CIP was then changed to reflect construction in 2007. <br /> <br />The City also submitted a DNR Trailway Grant application for the segment on the south side in between Silver Lake Road and Long Lake Road (segments 9-10) on February 28, 2006. The City <br /> will know if we were successful or not with this grant application in June of this year. <br /> <br />Ramsey County Walkable Communities Work shop is scheduled for Thursday, May 11, 2006. 1:00 p.m. to 5:15 p.m. This workshop will be studying segments 9-10. <br /> <br />Gateway Monuments – On March 6, 2006, the City Council indicated a desire to look into the feasibility and costs associated with constructing the County Road 10 Gateway Monument Signage. <br /> There are three monument signs under consideration–East Entrance, West Entrance, and Civic District Trail Gateway. The City’s consultant has submitted letter proposal to look into developing <br /> a schematic design for each of these signs. This will be presented to City Council on May 1, 2006. Are there any comments the Commission would like to provide? <br /> <br />Facility Guide Update – On Hold; waiting for decisions on Mounds View Community Center <br /> <br />Silver Lake Road Sidewalk Project – <br />On April 24, 2006, the City Council adopted a resolution approving the plans and specifications and authorizing the advertisement for bids and setting a bid date for the Silver Lake <br /> Road Sidewalk Project. <br /> <br />The plan for this project is to construct a 6 ½ foot wide concrete sidewalk along the eastside of Silver Lake Road, from County Road H to County Road I. The current project schedule <br /> is as follows: <br />Approve plans / Set Bid Date April 24, 2006 <br />Submit formal Permit applications May 1, 2006 <br />Publish advertisement in local paper (Bulletin) June 14, 2006 <br />Publish advertisement in The Construction Bulletin June 14, 2006 <br />Bid opening July 6, 2006 <br />Award Construction Contract July 10, 2006 <br />Begin Construction July 24, 2006 <br />Complete Construction October 2006