Laserfiche WebLink
• <br /> which began December 8, 1986, and will conclude around <br /> January 26, will cost approximately $60,000. <br /> It is estimated that the second phase of the project <br /> which will begin around January 26, 1987, and will conclude <br /> around May 25, will cost approximately $57,000. <br /> Total cost of the project would then be <br /> approximately $117, 000. <br /> Thus far, a total of $60, 000 hAs been commited to <br /> by the County and City, a pledge of $12, 000 by the Anoka <br /> County Chamber of Commerce, and two individual contributions <br /> of $1, 000 each. The remaining balance to be raised is $43,000. <br /> D. SOURCE OF FUNDING <br /> The Minnesota Olympic Facility Study Team has no <br /> "legal" identity. Therefore the monies from the City and <br /> the County are being processed through the City of Blaine, <br /> using C.D.B.G. funds as their source. <br />