1 <br /> 1. EXECUTIVE SUMMARY <br /> 1 This project has been entitled the 2002 Street and Utility Improvement Project. This <br /> project provides for the street and utility reconstruction on Wilson Street from 30th <br /> 1 Avenue to 32nd Avenue, Harding Street from 30th Avenue to 31 st Avenue; 31 st Avenue <br /> from Edward Street to Silver Lake Road; and 32nd Avenue from Edward Street to Belden <br /> Drive. <br /> 1 This Feasibility Report outlines the proposed reconstruction of approximately 3,900 feet <br /> of 30-foot(30') urban section streets, complete with bituminous paving and concrete curb <br /> 1 and gutter. Also proposed is the replacement of approximately 3,900 feet of water main, <br /> and 2,300 feet of sanitary sewer main, approximately 63 water services, and the new <br /> installation of 3,200 feet of storm sewer ranging from 36 inches (36")to 66 inches(66") <br /> 1 in diameter. <br /> A total estimated project cost is $2,200,000. Funding for the project will come from the <br /> 1 City's street and utility reconstruction funds, the Minnesota Department of Natural <br /> Resources, and special assessments. <br /> 1 The project reconstruction can be completed, including the first lift of bituminous and all <br /> restoration items, in 2002. The final lift of bituminous is proposed to be installed in <br /> 1 2003. <br /> This project is feasible,necessary, and cost effective from an engineering standpoint and <br /> should be constructed as proposed herein. <br /> 1 <br /> 1 <br /> 1 <br /> 1 - <br /> 1 <br /> i <br /> 1 <br /> 1 <br /> 1 City of St. Anthony—2002 Street and Utility Improvement Project <br /> Feasibility Report <br /> 1 WSB Project No. 1065-592 Page 1 <br />