Laserfiche WebLink
Tennis Courts <br /> Concrete $5,355.00 <br /> Maintenance Wall $1,570.00 <br /> Posts, Fence & Gates $14,000.00 <br /> Asphalt $19,800.00 <br /> Fill Materials $21,000.00 <br /> Miscellaneous Materials $5,000.00 <br /> (forms, pins, bolts, filter fabric, sealers etc...) <br /> Court Color Coat & Asphalt Filler $5,000.00 <br /> $71,725.00 <br /> *Electric costs to be determined <br /> "Paver & Crew costs to be determined <br /> (Midwest Asphalt) <br /> Budgeted $40,000.00, contingency remaining $84,000.00. Recommend we use <br /> approximately $60,000.00 of contingency to finish the project. <br /> The building is 95% complete so $24,000.00 should be plenty for any unforeseen <br /> expenditures. Sports Boosters payment of$15,000.00 is not included in the <br /> $84,000.00. <br />