2020 STREET AND UTILITY IMPROVEMENT PROJECT <br />FEASIBILITY REPORT <br />CITY OF ST. ANTHONY VILLAGE <br />WSB PROJECT NO. R-011648-000 PAGE 8 <br />6. PROJECT SCHEDULE <br />The proposed schedule for this improvement is as follows: <br />Task Completion Date <br />1. Order Feasibility Report.......................................................................................May 22, 2018 <br />2. Accept Feasibility Report and order plans and specifications...................September 11, 2018 <br />3. Accept Revised Feasibility Report and order plans and specifications .................April 9, 2019 <br />4. Hold first public information meeting...............................................................September 2019 <br />5. Approve plans/specifications, and order Ad for Bid .........................................November 2019 <br />6. Receive bids, compute assessments...................................................................January 2020 <br />7. Approve resolutions on improvement and assessment hearings ........................January 2020 <br />8. Hold second public information meeting ............................................................February 2020 <br />9. Public hearing for project, assessments, award bid, call bond sale...................February 2020 <br />10. Award sale of bonds ...............................................................................................March 2020 <br />11. Begin construction.............................................................................................May/June 2020 <br />12. Certify assessments to a county auditor................................................................August 2020 <br />13. Substantial completion of construction............................................................September 2020 <br />14. Final completion of construction (Final wear paving along <br />Reconstructed roadways and mill/overlay along Silver Lane) ..................................June 2021 <br />105