12/4/2024 <br />4 <br />PETROFUND REIMBURSMENT <br />•Portions of construction and WSB engineering costs  <br />eligible for reimbursement via Petrofund  <br />•*Only costs associated with management and  <br />disposal of petroleum contaminated soil <br />•Does not include actual tank removal <br />•Must be grossly contaminated / petroleum saturated <br />•Loading, hauling, stockpiling, disposal, backfill <br />•Up to 200 cubic yards, more if needed with prior  <br />MPCA approval <br />•Approx. 25% of total costs may be eligible <br />PROPOSED PROJECT SCHEDULE <br />•Council Approves Plans December 10, 2024 <br />•Plans, Specs, Bid Solicitation January 2025 <br />•Award Contract February 2025 <br />•UST and Canopy Removal March 2025 <br />•Documentation Report and Petrofund Application* April 2025 <br />*Dept of Commerce Petrofund application review and reimbursement  <br />can take up to one year <br />35