Laserfiche WebLink
EXHIBIT B <br />Project Budget <br />ESTIMATED COST <br />The preliminary estimated cost of construction is shown in the table below. It is estimated that the project <br />costs will total $522,000, including a 10% construction contingency and 20% indirect costs, as shown in <br />the table below. The cost of monitoring is not included. <br />Task <br />Estimated Cost <br />Storm Pond Cleanout <br />$95,000 <br />Pump System/Intake* <br />$64,000 <br />Forcemain Distribution and Irrigation Retrofit* <br />$189,000 <br />Educational Signs* <br />$4,500 <br />Mobilization, Erosion Control, and Site Restoration <br />$42,000 <br />Construction Subtotal <br />$394,500 <br />10% Contingency <br />$40,000 <br />Construction Total <br />$434,500 <br />20% Indirect <br />$87,000 <br />Total <br />$522,000 <br />*Indicates Metropolitan Council funded item <br />EXHIBIT B <br />