Laserfiche WebLink
Ms. Rachel Juba <br />June 15, 2017 <br />Page 2 <br />4.) Shift the watermain further into the roadway on 141St Street by shifting MH -(25) to the <br />north/northeast to the center of the westbound driving lane. <br />5.) Switch the `8" -90 degree bend' with an `8"x6" Tee with a rodded plug' at the west end of 141St <br />Street to allow for future watermain extensions. <br />6.) The storm sewer pipe sizes do not match the Rational Storm Sewer Design Tabulation submitted. <br />Revise the storm sewer design to reflect the pipe sizes, structure locations, and drainage areas of <br />the current design. <br />7.) Update the street typical sections for the 4' Addition. <br />8.) Delete the label in the `Rectangular Catch Basin with Poured In -Place Invert' detail that says `set <br />casting in mortar bed, use adjust rings as needed' <br />9.) Correct north arrow on Sheet 4 of 8 <br />Thank you for the opportunity to provide comments on this project. If you have any questions, please do <br />not hesitate to contact me at 651-286-8463. <br />Sincerely, <br />WSB & Associates, Inc. <br />Mark Erichson, PE <br />City Engineer <br />cc: Steve Duff, Senior Engineering Technician (email only) <br />Fran Hagen II, Westwood Professional Services (email only) <br />