Base Bid
<br />Parking Lot, Trail,
<br />Electrical Upgrades
<br />Alternate Bid 1
<br />Parking Lot Light
<br />Alternate Bid 2
<br />South Electrical
<br />Receptacle
<br />Total Base Bid +
<br />Alternate Bid 1 +
<br />Alternate Bid 2
<br />Engineer’s Estimate $170,890.00 $14,000.00 $8,000.00 $192,890.00
<br />Omann Contracting
<br />Companies, Inc. $139,926.50 $8,480.00 $10,400.00 $158,806.50
<br />Clark Companies $154,785.00 $23,500.00 $13,500.00 $191,785.00
<br />Blackstone Contractors,
<br />LLC $158,827.01 $7,927.50 $3,911.25 $170,665.76
<br />Kevin Dunaway dba
<br />Dunaway Construction $165,565.50 $5,692.00 $3,905.00 $175,162.50
<br />Valley Paving, Inc. $174,891.00 $6,200.00 $4,200.00 $185,291.00
<br />Winberg Companies LLC $175,887.08 $6,369.30 $4,100.25 $186,356.63
<br />Pember Companies, Inc. $175,977.70 $6,035.00 $4,150.00 $186,162.70
<br />Sunram Construction,
<br />Inc. $176,265.00 $6,275.00 $4,100.00 $186,640.00
<br />New Look Contracting,
<br />Inc. $178,520.65 $7,200.00 $4,625.00 $190,345.65
<br />Bituminous Roadways,
<br />Inc. $181,672.50 $6,395.00 $4,385.00 $192,452.50
<br />Dreamland Contracting
<br />LLC $184,825.34 $12,475.84 $9,588.34 $206,889.52
<br />Urban Companies, LLC $205,236.50 $9,000.00 $5,258.00 $219,494.50
<br />After including construction contingency and anticipated project indirect costs, the estimated total
<br />project costs are itemized below.
<br />Base Bid
<br />Parking Lot, Trail,
<br />Electrical Upgrades
<br />Alternate Bid 1
<br />Parking Lot Light
<br />Alternate Bid 2
<br />South Electrical
<br />Receptacle
<br />Total Base Bid +
<br />Alternate Bid 1 +
<br />Alternate Bid 2
<br />Low Bid (Omann) $139,926.50 $8,480.00 $10,400.00 $158,806.50
<br />+10% Contingency $13,992.65 $848.00 $1,040.00 $15,880.65
<br />+30% Indirect $41,977.95 $2,544.00 $3,120.00 $47,641.95
<br />Total Project $195,897.10 $11,872.00 $14,560.00 $222,329.10
|