Ms. Katie Larsen <br />06/03/2020 <br />Page 7 <br />7. Applicant shall adjust location of Hydrant 8 so that it does not interfere with retaining <br />wall construction. <br />8. Review the watermain layout between Lots 14 and 15. Applicant shall center the <br />watermain between the proposed lots while maintaining at least 15 feet of separation <br />between the structures and the watermain. Adjust easements as needed. <br />9. The City no longer needs the 12" watermain to be extended along Hodgson Rd between <br />the north property line and the northern entrance with this development. <br />10. Applicant shall specify material and size of casing pipe on plans for watermain crossings <br />at Hodgson. Per Anoka County, HDPE watermain may be drilled without casing pipe if <br />applicant finds HDPE watermain to be more cost effective for the crossings. <br />11. Applicant shall state the pipe material in the plan and profile views. <br />• Sanitary Sewer <br />The project site is currently not served by municipal sanitary sewer. The City of Lino Lakes is <br />working on a trunk sanitary sewer project including a Lift Station and forcemain to serve <br />approximately 60 acres. This service area includes the Lyngblomsten site and an unserviced area <br />east of Hodgson Road. The Lyngblomsten project proposes serving the development with municipal <br />sanitary sewer and services extended to each lot. <br />Comments: <br />1. The applicant shall note the sewer connection location at the lift station will need to be <br />adjust as the City finalizes the construction plans for this project. <br />Noted. <br />The invert at the lift station will need to be modified, it should be at 889.XX. <br />This outlet invert has been labeled. (AJA 2020-05.08) <br />City staff with provide current version of the lift station layout. Please update <br />Lyngblomsten plans accordingly. <br />The applicant shall provide profile views of the proposed sanitary sewer in the <br />construction plans. <br />Profiles will be accomplished with the final construction plans. <br />Staff will review sanitary sewer profiles once layout comments have been addressed <br />and the profile views are updated. General profile comments include: <br />a. Applicant shall adjust overlapping pipe and manhole labels <br />b. Applicant shall indicate that pipe should be SDR 26 for pipes over 20-ft deep <br />c. Applicant shall review that all plan view limits match the profile view limits on the <br />profile sheets. See sheet C1.82C as an example. Profile view includes MH 4, but <br />plan view does not. <br />d. Applicant shall review pipe material labels on all profiles to ensure that they <br />match what is shown in the plan view. See sheet C1.82D as an example. The <br />pipe between MH 1A and MH 1 B is shown as PVC in the plan view and RCP in <br />the profile view. <br />The utility crossings at Hodgson will require casing pipes and Manholes on each side of <br />the roadway. <br />Casing pipes below Hodgson have been provided on the utility plans. (AJA 2020-05.08) <br />Applicant shall specify material and size of casing pipe on plans. Casing pipe for the 8" <br />sanitary sewer shall be at least 20" in diameter. <br />Lyngblomsten Preliminary Plat Engineering Review <br />