Contractor shall pay Owner $300 for each day that expires after the time specified in <br />Paragraph 4.02A for Substantial Completion until the Work is Substantially Complete. <br />B. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the <br />remaining Work within the Contract Time or any proper extension thereof granted by <br />Owner, Contractor shall pay Owner $300 for each day that expires after the time specified <br />in Paragraph 4.02B for completion and readiness for Final Payment until the Work is <br />completed and ready for Final Payment. <br />ARTICLE 5 - CONTRACT PRICE <br />5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract <br />Documents an amount in current funds as follows: <br />A. For all Work at the prices stated in Contractor's Bid, attached hereto as an exhibit. The Bid <br />prices for Unit Price Work set forth as of the Effective Date of the Agreement are based on <br />estimated quantities. As provided in Paragraph 11.03 of the General Conditions, estimated <br />quantities are not guaranteed, and determinations of actual quantities and classifications <br />are to be made by Engineer as provided in Paragraph 9.07 of the General Conditions. <br />B. Original Contract Amount is based on the Total Base Bid of [fill in after contract award]. <br />ARTICLE 6 - PAYMENT PROCEDURES <br />6.01 Submittal and Processing of Payments <br />A. Contractor shall submit Applications for Payment in accordance with Article 14 of the <br />General Conditions. Applications for Payment will be processed by Engineer as provided in <br />the General Conditions. <br />6.02 Progress Payments; Retainage <br />A. Owner shall make progress payments on account of the Contract Price on the basis of <br />Contractor's Applications for Payment, monthly during performance of the Work as <br />provided in Paragraphs 6.02.A1 and 6.02.A2 below. All such payments will be measured by <br />the Schedule of Values established in Paragraph 2.07.A of the General Conditions (and in <br />the case of Bid Unit Price Work based on the number of units completed) or, in the event <br />there is no Schedule of Values, as provided in the General Requirements: <br />1. Prior to Substantial Completion, progress payments will be made in an amount equal <br />to the percentage indicated below, but in each case, less the aggregate of payments <br />previously made and less such amounts as Engineer may determine or Owner may <br />withhold, including but not limited to liquidated damages, in accordance with <br />Paragraph 14.02 of the General Conditions: <br />a. 95 percent of Work completed (with the balance being retainage). <br />b. 95 percent of cost of materials and equipment not incorporated in the Work (with <br />the balance being retainage). <br />2. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total <br />payments to Contractor to 100 percent of the Work completed, less such amounts as <br />Engineer shall determine in accordance with Paragraph 14.02.135 of the General <br />Conditions and less 200 percent of Engineer's estimate of the value of Work to be <br />completed or corrected as shown on the tentative list of items to be completed or <br />corrected attached to the certificate of Substantial Completion. <br />AGREEMENT FORM <br />© 2015 Stantec 1 193803415 00 52 10 - 2 <br />