MnDOT Contract No.: 1060495
<br />-6-
<br />Payable DCP and State Encumbering and Paying TH Portion
<br />documents for rights-of-way and easements, construction permits, and other permits and sanctions
<br />required for State participation construction covered under this Agreement.
<br />4.2. The County will convey to the State by quit claim deed, all newly acquired rights needed for the continuing
<br />operation and maintenance of the Trunk Highway, if any, upon completion of the Project, at no cost or
<br />expense to the State.
<br />4.3. The County will comply with Minnesota Statutes § 216D.04, subdivision 1(a), for identification, notification,
<br />design meetings, and depiction of utilities affected by the contract construction.
<br />4.4. The City will submit to the State's Utility Engineer an original permit application for all utilities owned by
<br />the City to be constructed upon and within the Trunk Highway Right-of-Way. Applications for permits will
<br />be made on State form "Application for Utility Permit on Trunk Highway Right-of-Way" (Form 2525).
<br />4.5. Limited Use Permit. The County will obtain, through the District's Right-of-Way Area Manager, a Limited
<br />Use Permit (LUP), currently LUP 8204-0095, to cover the County's liability responsibilities of the shared use
<br />path to be constructed upon the State's Right-of-Way.
<br />5. Maintenance by the City
<br />Upon completion of the Project, the City will provide the following without cost or expense to the State:
<br />5.1. Roadways. Maintenance of 60th Street North (South Frontage Road) and Keats Avenue one-way exit.
<br />Maintenance includes, but is not limited to, snow, ice and debris removal, resurfacing, seal coating, and
<br />any other maintenance activities according to accepted City maintenance practices.
<br />5.2. Storm Sewers. Routine maintenance of storm sewer facilities construction where shown in Exhibit A.
<br />Routine maintenance includes, but is not limited to, removal of sediment, debris, vegetation, and ice from
<br />grates and catch basins, and any other maintenance activities necessary to preserve the facilities and to
<br />prevent conditions such as flooding, erosion, or sedimentation, this also includes informing the District
<br />Maintenance Engineer of any needed repairs within the trunk highway right-of-way.
<br />5.3. Municipal Utilities. Maintenance of any municipal-owned utilities construction, without cost or expense to
<br />the State.
<br />5.4. Lighting. Maintenance and ownership of lighting facilities construction where shown in Exhibit B.
<br />Maintenance of electrical lighting systems includes everything within the system, from the point of
<br />attachment to the power source or utility, to the last light on the feed point, including but not limited to
<br />re-lamping of lighting units or replacing of LED luminaires, repair or replacement of all damaged luminaire
<br />glassware, loose connections, luminaires when damaged or when ballasts fail, photoelectric control on
<br />luminaires, defective starter boards or drivers, damaged fuse holders, blown fuses, knocked down poles
<br />including wiring within the poles, damaged poles, pull boxes, underground wire, damaged foundations,
<br />equipment pad, installation of approved splices or replacement of wires, repair or extending of conduit,
<br />lighting cabinet maintenance including photoelectric cell, electrical distribution system, Gopher State One
<br />Call (GSOC) locates, and painting of poles and other equipment. The City will be responsible for the hook
<br />up cost and application to secure an adequate power supply to the service pad or pole and will pay all
<br />monthly electrical service expenses necessary to operate the lighting facility.
<br />5.5. Additional Drainage. No party to this Agreement will drain any additional drainage volume into the storm
<br />sewer facilities constructed under the construction contract that was not included in the drainage for
<br />which the storm sewer facilities were designed, without first obtaining written permission to do so from
<br />the other party.
<br />5.6. Future Responsibilities. Upon completion of the 60th Street North (South Frontage Road) construction, the
<br />City will accept full and total responsibility and all obligations and liabilities arising out of or by reason of
|